GCB-Final | 4/15/2011 | 4/18/2011 | 4/18/2011 | A | PASS |
Mike Jordan
|
|
|
All issues were resolved. Card was signed, structural final ok.
|
GCB-Final | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | FAIL |
Mike Jordan
|
|
|
FinalRich @ ###-####Call for access. Needs to insulate crawl space, caulk all penetrations at garage common wall. Contractor notified and correction notice issued.
|
GCB-Energy | 12/30/2010 | 1/3/2011 | 1/3/2011 | A | PASS |
Dave Hannah
|
|
|
Scope: EnergyContact: Rich @ ###-####
|
GCB-Framing | 12/30/2010 | 1/3/2011 | 1/3/2011 | A | PASS |
Dave Hannah
|
|
|
Scope: FramingContact: Rich @ ###-####
|
GCB-Framing | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | FAIL |
Mike Jordan
|
|
|
Scope: FramingContact: Rich @ ###-####. Needs tp provide new truss engineering or correct trusses T13 - T09 show bearing point in middle of truss with no wall to bear on below. ok to insulate.
|
GCB-Footing | 11/24/2010 | 11/29/2010 | 11/30/2010 | A | PASS |
Dave Hannah
|
|
|
Scope: FootingsContact: Rich @ ###-#### contractor pouring ftgs will finish cleaning out frost and mud before they place concrete.
|
Plan assigned to (SRZ) | 11/9/2010 | 11/9/2010 | 11/10/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/9/2010 | | 11/10/2010 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 11/10/2010 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2010 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 11/10/2010 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 11/5/2010 | | DONE |
|
|
|
|