GCB-Final | 1/27/2011 | 1/28/2011 | 1/28/2011 | A | PASS |
Mike Jordan
|
|
|
Scope: FinalContact: Don @ ###-####Call for access. final ok.
|
GCB-Footing | 1/13/2011 | 1/13/2011 | 1/13/2011 | P | PASS |
Mike Jordan
|
|
|
Footing& Foundation inspection-Don Phone #: ###-####
|
GCB-Fndatn/slab ins/fld vent | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | CANC |
Mike Jordan
|
|
|
Scope: FoundationContact: Don @ ###-####
|
GCB-Footing | 1/11/2011 | 1/12/2011 | 1/12/2011 | A | CANC |
Mike Jordan
|
|
|
Scope: FootingsContact: Don @ ###-####.Cancelled by Don via phone call.
|
Issue and Courier | | | 12/6/2010 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 11/19/2010 | 11/19/2010 | 12/3/2010 | | DONE |
Sam Zahorka
|
|
|
Failed 1st Review 11-23-10
|
Routing - PLAN CHECK | 12/3/2010 | | 12/3/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/19/2010 | | 11/23/2010 | | FAIL |
Sam Zahorka
|
|
|
|
Telephone call | | | 11/23/2010 | | DONE |
Sam Zahorka
|
|
|
I spoke with a Dawn Roell the new applicant for this project. I verified the project has changed from one shed to two smaller sheds. I requested some corrections and he said he would get them to me next week. A 1 hour wall assembly is required due to fire separation distance of 5 ft. or a new site plan with a setback of 10 ft., a letter or revised drawings from the engineer stating the structure is designed for a 25 psf roof live load, and a drawing of the foundation extending a minimum of 12 inches below finished grade. I also called Leon w/ Garden city and let him know the status of the permit. SRZ
|
1st review completed | | | 11/23/2010 | | FAIL |
Sam Zahorka
|
|
|
The project has changed from one shed to two smaller sheds. I requested some corrections and he said he would get them to me next week. A 1 hour wall assembly is required due to fire separation distance of 5 ft. or a new site plan with a setback of 10 ft., a letter or revised drawings from the engineer stating the structure is designed for a 25 psf roof live load, and a drawing of the foundation extending a minimum of 12 inches below finished grade. I also called Leon w/ Garden city and let him know the status of the permit. SRZ
|
Application received | | 11/19/2010 | 11/19/2010 | | DONE |
|
|
|
|
Application received | | | 11/17/2010 | | DONE |
|
|
|
|