Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberGCB11-00009
StatusUnder Review
Name ROB GODSILL
Site Address 7135 W STATE ST
Project NameBLD2011-00008
Customer Number 
ePlanReviewNo
Description
Bob's Sunrise Cafe - **ALL MECHANICAL WORK INCLUDING: GAS PIPING, TYPE 1 COMMERCIAL COOKING HOODS, AND MAKE UP AIR UNITS (MAU) ARE UNDER A SEPARATE MECHANICAL PERMIT. NO CERTIFICATE OF OCCUPANCY SHALL BE ISSUED UNTIL THE MECHANICAL PERMIT IS FINALED.** To remodel the interior of an existing 4,974 square foot restaurant. Work to include: construct new walls in kitchen area per plans; install a new sink, new exit lighting, new emergency lighting, new custom built in walk in freezer and refrigerator; remove and replace water heater; apply new epoxy wall glaze finishes; install new fixed stool seating and raised seating counter; install new ceiling finishes per plans; related interior finishes in compliance with chapter 8 of the 2009 IBC; and plumbing, electrical work. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. NOTE: This building is fully fire sprinklered. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department and will require a separate permit. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final5/23/20115/24/20115/24/2011APART
DetailsDave Hannah
FinalRob @ ###-####Call in advance ok for temp occ ok for perm occ after they fix door hardwear on two back doors and get mec final
GCB-Framing4/5/20114/6/20114/6/2011APASS
DetailsDave Hannah
FramingRob @ ###-####Call in advance
Case Summary (GCB)  4/6/2011 DONE
CHANGE STATUS TO (ISS)  4/5/2011 DONE
Plan assigned to (SRZ)2/22/20112/22/20113/22/2011 DONE
DetailsSam Zahorka
Routing - PLAN CHECK3/22/2011 3/22/2011 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/22/2011 DONE
DetailsSam Zahorka
Issue and Courier  3/22/2011 DONE
Plan resubmittals received  3/21/2011 DONE
mechanical resubmittals received
Routing - PLAN CHECK3/2/2011 3/21/2011 PEND
DetailsSam Zahorka
Pending new plans from Garden City.
Telephone call  3/16/2011 DONE
DetailsSam Zahorka
I spoke with Bill Matter the Architect. He stated Mechanical corrections were almost completed and should be resubmitted shortly. SRZ
Telephone call  3/11/2011 DONE
DetailsSam Zahorka
I called the Applicant Rob to check on the status of the Mechanical plan review corrections. Left a message.
1st review completed  3/2/2011 DONE
DetailsSam Zahorka
Failed Mechanical Review
Routing - Mechanical Review2/28/2011 3/2/2011 FAIL
DetailsTroy James
All Mechanical work removed from this permit and moved to a new mechanical permit. IF there are any questions contact Sam Zahorka ###-####
Routing - PLAN CHECK2/22/2011 2/28/2011 PASS
DetailsSam Zahorka
Application received  2/18/2011 DONE