GCB-Final | 5/23/2011 | 5/24/2011 | 5/24/2011 | A | PART |
Dave Hannah
|
|
|
FinalRob @ ###-####Call in advance ok for temp occ ok for perm occ after they fix door hardwear on two back doors and get mec final
|
GCB-Framing | 4/5/2011 | 4/6/2011 | 4/6/2011 | A | PASS |
Dave Hannah
|
|
|
FramingRob @ ###-####Call in advance
|
Case Summary (GCB) | | | 4/6/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/5/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 2/22/2011 | 2/22/2011 | 3/22/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/22/2011 | | 3/22/2011 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 3/22/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/21/2011 | | DONE |
|
|
|
mechanical resubmittals received
|
Routing - PLAN CHECK | 3/2/2011 | | 3/21/2011 | | PEND |
Sam Zahorka
|
|
|
Pending new plans from Garden City.
|
Telephone call | | | 3/16/2011 | | DONE |
Sam Zahorka
|
|
|
I spoke with Bill Matter the Architect. He stated Mechanical corrections were almost completed and should be resubmitted shortly. SRZ
|
Telephone call | | | 3/11/2011 | | DONE |
Sam Zahorka
|
|
|
I called the Applicant Rob to check on the status of the Mechanical plan review corrections. Left a message.
|
1st review completed | | | 3/2/2011 | | DONE |
Sam Zahorka
|
|
|
Failed Mechanical Review
|
Routing - Mechanical Review | 2/28/2011 | | 3/2/2011 | | FAIL |
Troy James
|
|
|
All Mechanical work removed from this permit and moved to a new mechanical permit. IF there are any questions contact Sam Zahorka ###-####
|
Routing - PLAN CHECK | 2/22/2011 | | 2/28/2011 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | | 2/18/2011 | | DONE |
|
|
|
|