GCB-Final | 8/4/2011 | 8/5/2011 | 8/5/2011 | A | PASS |
Tom Arcoraci
|
|
|
FinalMark @ ###-####Call for access - AM Inspection
|
CHANGE STATUS TO (ISS) | | | 8/5/2011 | | DONE |
Sam Zahorka
|
|
|
|
GCB-Energy | 6/14/2011 | 6/15/2011 | 6/15/2011 | A | PASS |
Mike Jordan
|
|
|
EnergyMark @ ###-####Call in advance for access. ok to sheet rock.
|
GCB-Framing | 6/13/2011 | 6/14/2011 | 6/14/2011 | A | PASS |
Mike Jordan
|
|
|
FramingMark @ ###-####. Ok to insulate.
|
GCB-Framing | 6/9/2011 | 6/13/2011 | 6/13/2011 | A | CANC |
Mike Jordan
|
|
|
Framing (Shearnail)Mark @ ###-####Call in advance
|
Plan resubmittals received | | | 6/8/2011 | | PASS |
Troy James
|
|
|
|
Routing - Mechanical Review | 6/8/2011 | | 6/8/2011 | | PASS |
Troy James
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 5/27/2011 | 5/31/2011 | 5/31/2011 | A | PART |
Dave Hannah
|
|
|
Foundation Mark @ ###-####Call in advance - AM Inspection part grouting under column plat ok to cover
|
GCB-Fndatn/slab ins/fld vent | 4/22/2011 | 4/25/2011 | 4/25/2011 | A | PASS |
Dave Hannah
|
|
|
FoundationContractor @ ###-####Call in advance - Inspection before noon back part
|
GCB-Footing | 4/22/2011 | 4/25/2011 | 4/25/2011 | A | PASS |
Dave Hannah
|
|
|
FootingsContractor @ ###-####Call for access - Inspection before Noon
|
Plan assigned to (SRZ) | 3/29/2011 | 3/29/2011 | 4/14/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/29/2011 | | 4/14/2011 | | PASS |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 4/14/2011 | | 4/14/2011 | | PASS |
Troy James
|
|
|
calcs approved with notes
|
1st review completed | | | 4/14/2011 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 4/14/2011 | | DONE |
|
|
|
|
Application received | | | 3/28/2011 | | DONE |
|
|
|
|