GCB-Final | 10/25/2011 | 10/26/2011 | 10/27/2011 | A | PASS |
Dave Hannah
|
|
|
Bill @ ###-####Call for access
|
GCB-Final | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | CANC |
Dave Hannah
|
|
|
Bill @ ###-####Noon inspection pleaseCall in advance
|
GCB-Energy | 8/10/2011 | 8/11/2011 | 8/11/2011 | A | PASS |
Dave Hannah
|
|
|
EnergyBill @ ###-####
|
GCB-Framing | 8/5/2011 | 8/8/2011 | 8/8/2011 | A | PASS |
Mike Jordan
|
|
|
FramingBill @ ###-####Noon inspection please
|
Plan resubmittals received | | | 8/8/2011 | | PASS |
|
|
|
manual j resubmittal
|
Routing - Mechanical Review | 8/8/2011 | | 8/8/2011 | | PASS |
Troy James
|
|
|
manual j resubmitted
|
Telephone call | | | 8/8/2011 | | DONE |
|
|
|
emailed geoff manual j ready to be picked at garden city bld dept
|
GCB-Framing | 7/25/2011 | 7/26/2011 | 7/27/2011 | A | PART |
Dave Hannah
|
|
|
Framing (Shear Nail)paul @ ###-####Call in advance - PM Inspection ok to cover ext
|
GCB-Stem wall | 6/28/2011 | 6/29/2011 | 6/29/2011 | A | PASS |
Dave Hannah
|
|
|
StemwallShane @ ###-####PM Inspection Please
|
GCB-Footing | 6/27/2011 | 6/28/2011 | 6/28/2011 | A | PASS |
Dave Hannah
|
|
|
FootingsRyan @ ###-####Call in advance - PM Inspection
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 6/21/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 5/31/2011 | | 6/21/2011 | | DONE |
Sam Zahorka
|
|
|
1st review completed
|
Routing - PLAN CHECK | 6/13/2011 | | 6/21/2011 | | PASS |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 6/20/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/1/2011 | | 6/13/2011 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 6/13/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 5/31/2011 | | 6/1/2011 | | PASS |
Troy James
|
|
|
|
Application received | | 5/31/2011 | 5/31/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 5/31/2011 | | DONE |
|
|
|
|
Application received | | | 5/27/2011 | | DONE |
|
|
|
|