GCB-Final | 11/18/2011 | 11/18/2011 | 11/18/2011 | P | PASS |
Dave Hannah
|
|
|
kent Phone #: ###-####
|
GCB-Final | 11/4/2011 | 11/7/2011 | 11/7/2011 | A | FAIL |
Mike Jordan
|
|
|
Kelly @ ###-####Call for access. Provide CO2 detector upstairs, Provide required energry cert and blower door test results and post as required. Correction notice was issued.
|
GCB-Energy | 8/25/2011 | 8/26/2011 | 8/26/2011 | A | FAIL |
Mike Jordan
|
|
|
Kelly @ ###-####AM Inspection. No mech. inspection performed. Do Not cover.
|
GCB-Framing | 8/19/2011 | 8/22/2011 | 8/22/2011 | A | PART |
Dave Hannah
|
|
|
FramingKelly @ ###-####AM Inspection ok to insulate after mec r/i has been approved
|
GCB-Stem wall | 7/18/2011 | 7/19/2011 | 7/19/2011 | A | CANC |
Mike Jordan
|
|
|
StemwallJerry @ ###-####PM Inspection Please
|
GCB-Fndatn/slab ins/fld vent | 7/18/2011 | 7/19/2011 | 7/19/2011 | A | PASS |
Mike Jordan
|
|
|
FoundationJerry @ ###-####PM Inspection Please
|
GCB-Footing | 7/15/2011 | 7/18/2011 | 7/18/2011 | A | PASS |
Dave Hannah
|
|
|
FootingsDane @ ###-####Call in advance
|
Routing - PLAN CHECK | 7/12/2011 | | 7/12/2011 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 7/12/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 6/17/2011 | | 7/12/2011 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Pending corrections.
|
Plan resubmittals received | | | 7/7/2011 | | DONE |
|
|
|
|
1st review completed | | | 6/28/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/22/2011 | | 6/28/2011 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 6/22/2011 | | 6/22/2011 | | PASS |
Troy James
|
|
|
|
Routing - Mechanical Review | 6/17/2011 | | 6/21/2011 | | FAIL |
Troy James
|
|
|
no acca manual calcs, called applicant and left message
|
Application received | | 6/17/2011 | 6/17/2011 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 6/17/2011 | | DONE |
|
|
|
|
Application received | | | 6/13/2011 | | DONE |
|
|
|
|