GCB-Final | 10/31/2012 | 11/1/2012 | 11/1/2012 | A | PASS |
Tom Arcoraci
|
|
|
Dave @ ###-#### bld final ok
|
GCB-Courtesy | 5/10/2012 | 5/11/2012 | 5/11/2012 | A | PASS |
Mike Jordan
|
|
|
Dave @ ###-####
|
GCB-Courtesy | 4/25/2012 | 4/25/2012 | 4/26/2012 | A | PASS |
Dave Hannah
|
|
|
Dave @ ###-#### Requested an afternoon courtesy inspection today. ok to ext permit
|
GCB-Framing | 9/27/2011 | 9/28/2011 | 9/28/2011 | A | PART |
Mike Jordan
|
|
|
Dave ###-#### or Marge ###-####--Final Elevation Certificate Recieved:Tope of bottom floor 2658.5. Needs electrical rough in inspection. Framing to this point ok. Will recall framing inspection of electrical rough in has been completed.
|
GCB-Fndatn/slab ins/fld vent | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PART |
Dave Hannah
|
|
|
Dave @ ###-#### trebar in walls marked setback ok
|
GCB-Footing | 9/2/2011 | 9/6/2011 | 9/6/2011 | A | PASS |
Mike Jordan
|
|
|
DAVE @ ###-####CALL IN ADVANCE
|
Issue and Courier | | | 8/24/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 8/12/2011 | 8/12/2011 | 8/23/2011 | | DONE |
Sam Zahorka
|
|
|
Waiting for flood plain info.
|
Routing - PLAN CHECK | 8/23/2011 | | 8/23/2011 | | PASS |
Sam Zahorka
|
|
|
Received telephone call from Garden CIty. Elevation certificate has been received and the finished floor is above BFE.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 8/12/2011 | | 8/12/2011 | | FAIL |
Sam Zahorka
|
|
|
Garden City identified this parcel is in the flood plain and to hold permit until an elevation certificate is received.
|
1st review completed | | | 8/12/2011 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 8/11/2011 | | DONE |
|
|
|
|