GCB-Final | 3/26/2012 | 3/27/2012 | 3/27/2012 | A | PASS |
Dave Hannah
|
|
|
Rich @ ###-####
|
GCB-Energy | 12/8/2011 | 12/9/2011 | 12/9/2011 | A | PASS |
Mike Jordan
|
|
|
Richard @ ###-####Call for access
|
GCB-Framing | 12/6/2011 | 12/7/2011 | 12/7/2011 | A | PASS |
Mike Jordan
|
|
|
Richard @ ###-####PM Inspection - Call for access. ok to insulate.
|
GCB-Shearwall | 11/29/2011 | 11/30/2011 | 11/30/2011 | A | PART |
Mike Jordan
|
|
|
Richard ###-####Call for accessShear nail inspection. Needs to provide 1000lbs. straps from trimmer studs up to header and connect into top plate. Exterior shear nail ok. ok to cover.
|
GCB-Fndatn/slab ins/fld vent | 11/16/2011 | 11/17/2011 | 11/17/2011 | A | PART |
Mike Jordan
|
|
|
Dane @ ###-####
|
GCB-Footing | 11/15/2011 | 11/16/2011 | 11/16/2011 | A | PASS |
Mike Jordan
|
|
|
Dane @ ###-####Pm Inspection - Call in advance
|
GCB-Footing | 11/14/2011 | 11/15/2011 | 11/16/2011 | A | CANC |
Dave Hannah
|
|
|
Dane @ ###-####PM Inspection
|
Issue and Courier | | | 11/9/2011 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 11/2/2011 | 11/2/2011 | 11/8/2011 | | DONE |
Sam Zahorka
|
|
|
1st review completed. need corrections
|
Meeting | | | 11/8/2011 | | DONE |
Sam Zahorka
|
|
|
Meeting with the residential designer. The designer Steve Uria with Ramtech design decided to provide CS-PF method at new garage fronts and requested plan review to red-line plans. Engineering was provided for garage footings and red-lined.
|
Routing - PLAN CHECK | 11/8/2011 | | 11/8/2011 | | PASS |
Sam Zahorka
|
|
|
Approved per red-lines.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/8/2011 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 11/7/2011 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/2/2011 | | 11/4/2011 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 11/4/2011 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 11/1/2011 | | DONE |
|
|
|
|