GCB-Final | 3/28/2012 | 3/28/2012 | 3/28/2012 | P | PASS |
Mike Jordan
|
|
|
MaryAnn-please call in advance Phone #: ###-####. Structural final ok.
|
GCB-Final | 3/19/2012 | 3/20/2012 | 3/20/2012 | A | PART |
Dave Hannah
|
|
|
Gary @ ###-#### 11 a.m. inspection May be seeking Temporary C of O ok for temp occ ok for perm after other trades ok and door hardwear is installed on door to up stairs
|
GCB-Framing | 2/28/2012 | 2/28/2012 | 2/28/2012 | P | PASS |
Dave Hannah
|
|
|
Gary @###-####
|
GCB-Framing | 2/24/2012 | 2/27/2012 | 2/27/2012 | A | CANC |
Dave Hannah
|
|
|
Gary @ ###-####Call in advance - PM Inspection
|
Plan assigned to (SRZ) | 2/23/2012 | 2/23/2012 | 2/24/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 2/23/2012 | | 2/24/2012 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2012 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/24/2012 | | DONE |
|
|
|
plan modification
|
Plan resubmittals received | | | 2/23/2012 | | |
|
|
|
Received 3 copies of sheet A-3.1 and taken to Sam Zahorka
|
Plan assigned to (SRZ) | 12/8/2011 | 12/8/2011 | 12/23/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 12/8/2011 | | 12/23/2011 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 12/23/2011 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 12/23/2011 | | DONE |
|
|
|
|
Application received | | | 12/7/2011 | | DONE |
|
|
|
|