GCB-Final | 4/26/2012 | 4/26/2012 | 4/26/2012 | P | PASS |
Mike Jordan
|
|
|
Eric @ ###-#### Call for access Requested afternoon inspection for today please. Structural final only ok. No card to sign.
|
GCB-Energy | 2/21/2012 | 2/22/2012 | 2/22/2012 | A | PASS |
Dave Hannah
|
|
|
Eric @ ###-####Noon inspection
|
GCB-Framing | 2/21/2012 | 2/22/2012 | 2/22/2012 | A | PASS |
Dave Hannah
|
|
|
Eric @ ###-####Noon inspection
|
GCB-Framing | 2/17/2012 | 2/21/2012 | 2/21/2012 | A | PART |
Dave Hannah
|
|
|
Eric @ ###-#### ok to insulatye c/n on site
|
GCB-Fndatn/slab ins/fld vent | 1/4/2012 | 1/5/2012 | 1/5/2012 | A | PASS |
Mike Jordan
|
|
|
Adam @ ###-####11 a.m. inspection
|
GCB-Fndatn/slab ins/fld vent | 12/30/2011 | 1/3/2012 | 1/4/2012 | A | CANC |
Dave Hannah
|
|
|
Adam @ ###-####Noon Inspection
|
GCB-Footing | 1/4/2012 | 1/4/2012 | 1/4/2012 | A | PASS |
Dave Hannah
|
|
|
|
GCB-Footing | 12/29/2011 | 12/30/2011 | 12/30/2011 | A | CANC |
Dave Hannah
|
|
|
Adam @ ###-####3:30 PM Inspection
|
Plan assigned to (SRZ) | 12/13/2011 | 12/13/2011 | 12/22/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 12/19/2011 | | 12/22/2011 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 12/22/2011 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2011 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 12/22/2011 | | DONE |
|
|
|
|
Routing - Mechanical Review | 12/13/2011 | | 12/19/2011 | | PASS |
Troy James
|
|
|
|
Application received | | | 12/12/2011 | | DONE |
|
|
|
|