GCB-Final | 6/18/2012 | 6/19/2012 | 6/19/2012 | A | PASS |
Dave Hannah
|
|
|
|
GCB-Courtesy | 5/10/2012 | 5/11/2012 | 5/11/2012 | A | PASS |
Mike Jordan
|
|
|
Scott @ ###-#### Inspection of soffit/fascia. Soffit has been removed and the 2 layers of 5/8 type x has been installed.
|
GCB-Energy | 4/23/2012 | 4/24/2012 | 4/24/2012 | A | PASS |
Dave Hannah
|
|
|
Scott @ ###-####
|
GCB-Framing | 4/23/2012 | 4/24/2012 | 4/24/2012 | A | PASS |
Dave Hannah
|
|
|
Scott @ ###-####
|
GCB-Framing | 4/18/2012 | 4/20/2012 | 4/20/2012 | P | PASS |
Dave Hannah
|
|
|
Scott @###-#### Requested PM Inspection for Friday. ok to insulate after mec rough in and fire place r/i is done
|
GCB-Fndatn/slab ins/fld vent | 3/2/2012 | 3/5/2012 | 3/5/2012 | A | PART |
Mike Jordan
|
|
|
Ian @ ###-####
|
GCB-Footing | 2/29/2012 | 3/2/2012 | 3/2/2012 | A | PASS |
Dave Hannah
|
|
|
Ian @ ###-####AM Inspection
|
GCB-Footing | 2/29/2012 | 3/1/2012 | 3/1/2012 | A | CANC |
Dave Hannah
|
|
|
Dave @ ###-####PM Inspection
|
Plan assigned to (SRZ) | 2/14/2012 | 2/14/2012 | 2/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 2/16/2012 | | 2/17/2012 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 2/17/2012 | | 2/17/2012 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 2/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 2/17/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Mechanical Review | 2/14/2012 | | 2/16/2012 | | FAIL |
Troy James
|
|
|
emailed correction to Travis, orientation and performance data
|
Application received | | | 2/13/2012 | | DONE |
|
|
|
|