GCB-Final | 10/3/2012 | 10/3/2012 | 10/3/2012 | P | PASS |
Dave Hannah
|
|
|
Trinity @ ###-#### Call for access
|
GCB-Final | 10/1/2012 | 10/1/2012 | 10/1/2012 | P | FAIL |
Dave Hannah
|
|
|
Trinity @ ###-#### needs to fine grade lot post address
|
GCB-Energy | 5/25/2012 | 5/29/2012 | 5/29/2012 | A | PASS |
Jim Sly
|
|
|
Kevin @ ###-####
|
GCB-Framing | 5/23/2012 | 5/24/2012 | 5/24/2012 | A | PASS |
Tom Arcoraci
|
|
|
Kevin @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 4/6/2012 | 4/9/2012 | 4/9/2012 | A | PASS |
Dave Hannah
|
|
|
Emanuel @ ###-####
|
GCB-Footing | 4/5/2012 | 4/6/2012 | 4/6/2012 | A | PASS |
Mike Jordan
|
|
|
Ryan @ ###-####
|
GCB-Footing | 4/4/2012 | 4/5/2012 | 4/5/2012 | P | CANC |
Mike Jordan
|
|
|
Ryan @ ###-#### PM Inspection. No inspection or time.
|
GCB-Footing | 4/3/2012 | 4/4/2012 | 4/4/2012 | P | CANC |
Dave Hannah
|
|
|
Ryan @ ###-#### PM Inspection
|
GCB-Footing | 4/2/2012 | 4/3/2012 | 4/3/2012 | P | NR |
Mike Jordan
|
|
|
Ryan @ ###-#### PM INspection. no one on site. no work at this time.
|
Issue and Courier | | | 3/22/2012 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 2/27/2012 | | 3/22/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/1/2012 | | 3/22/2012 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 3/21/2012 | | 3/22/2012 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines on drawings. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Mechanical Review | 3/20/2012 | | 3/21/2012 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 3/20/2012 | | |
|
|
|
|
1st review completed | | | 3/1/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Mechanical Review | 2/29/2012 | | 3/1/2012 | | FAIL |
Troy James
|
|
|
Corrections emailed to TML. Waiting for revised manual do to possibly irragation easements and need to show slab floor on report.
|
Routing - PLAN CHECK | 2/27/2012 | | 2/29/2012 | | FAIL |
Tim L. Woodard
|
|
|
Reffer to Plan Review Report. TLW
|
Application received | | | 2/23/2012 | | DONE |
|
|
|
|