GCB-Final | 8/14/2012 | 8/14/2012 | 8/14/2012 | P | PASS |
Dave Hannah
|
|
|
Steve @ ###-#### PM Inspection
|
GCB-Framing | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PART |
Mike Jordan
|
|
|
Robert @ ###-#### AM inspection requested Framing for facade. Needs to provide the correct track splice at corners and justify condition of simpson holdowns. ok to cover.
|
GCB-Shearwall | 7/11/2012 | 7/12/2012 | 7/12/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-####. Shear walls for new store front ok.
|
GCB-Ceiling Grid | 7/9/2012 | 7/10/2012 | 7/10/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-####. Hardlids ok to cover.
|
GCB-Framing | 7/6/2012 | 7/9/2012 | 7/9/2012 | P | CANC |
Mike Jordan
|
|
|
Robert @ ###-#### PM Inspection
|
GCB-Framing | 7/3/2012 | 7/5/2012 | 7/5/2012 | A | PART |
Dave Hannah
|
|
|
Robert @ ###-#### ext front soffiot ok to one side
|
GCB-Footing | 6/27/2012 | 6/28/2012 | 6/28/2012 | P | FAIL |
Mike Jordan
|
|
|
Robert @ ###-#### PM Inspection. Footing for compactor pad, Verts exceed the 16" O.C. spacing as shown on RFI and needs to provide 3" of clearance from bottom of footing to bottom of rebar. Correction notice was issued. MTI will verify repairs prior to placement and note on report.
|
GCB-Energy | 6/18/2012 | 6/19/2012 | 6/19/2012 | A | PASS |
Dave Hannah
|
|
|
Robert @ ###-#### ok to cover ext walls
|
GCB-Framing | 6/14/2012 | 6/15/2012 | 6/15/2012 | P | PASS |
Dave Hannah
|
|
|
Robert @ ###-#### PM Inspection ok to cover int walls ok to insulate ext walls
|
GCB-Footing | 5/24/2012 | 5/24/2012 | 5/24/2012 | P | PASS |
Tom Arcoraci
|
|
|
pending spec insp by mti
|
GCB-Footing | 5/23/2012 | 5/24/2012 | 5/24/2012 | A | CANC |
Tom Arcoraci
|
|
|
ROBERT @ ###-#### changed to pm per rob
|
GCB-Masonry | 5/21/2012 | 5/22/2012 | 5/22/2012 | A | PASS |
Mike Jordan
|
|
|
Robert @ ###-#### Inspection requested for as close to 9 a.m. as possible. 0 to 4ft. elevation at storefront. Also verified special inspections.
|
Plan assigned to (SRZ) | 5/15/2012 | 5/15/2012 | 5/18/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/15/2012 | | 5/18/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/18/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 5/18/2012 | | DONE |
Christina Prado
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 5/15/2012 | 5/16/2012 | 5/16/2012 | A | PART |
Dave Hannah
|
|
|
Rob @ ###-#### Call in advance to coordinate. Stemwall for canopy columns. Will have special inspection. Also noted to contractor that special inspection firm needs to be contracted by the owner or desighn professional as per IBC capter 17 sec1703.1.1 and sec1704.1. Will give general contractor until next inspection to have issue resolved.
|
GCB-Footing | 5/14/2012 | 5/15/2012 | 5/15/2012 | A | CANC |
Jim Sly
|
|
|
Robert @ ###-#### Late AM inspection requested.Late AM inspection requested.Call in advance Duplicate added in by mistake.......Approx 34 min for inspection. Jim Sly ###-####
|
GCB-Footing | 5/14/2012 | 5/15/2012 | 5/15/2012 | A | PASS |
Jim Sly
|
|
|
Robert @ ###-#### Late AM inspection requested. Call in advance Al lfootings OK .....Pending MTI special inspection, tests and approvals.
|
Plan resubmittals received | | | 5/15/2012 | | DONE |
Christina Prado
|
|
|
Received three sets of plans marked A0.0, A1.1, S2.1, S7.3, M1.0, M2.0, M3.1M4.0, M5.0, E5.0 & E6.0. Plans routed to Sam for further review
|
Plan assigned to (SRZ) | 3/19/2012 | 3/19/2012 | 4/16/2012 | | DONE |
Sam Zahorka
|
|
|
1st Review completed. Waiting for resubmittals.
|
Plan resubmittals received | | | 4/16/2012 | | |
|
|
|
|
Routing - PLAN CHECK | 4/16/2012 | | 4/16/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 4/16/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 3/19/2012 | | 4/11/2012 | | FAIL |
Sam Zahorka
|
|
|
Corrections sent to the architect.
|
1st review completed | | | 4/11/2012 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 4/11/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the architect Jeff Likes. Verbally discussed comments and corrections. He verified all fire wall compliance questions including horizontal projections and rated opening questions. All existing Firewalls concerning their continuity are in compliance. The existing glycol sprinkler protection in the front canopy will changed to a new dry system without conditioning of the canopy envelope.
|
Application received | | | 3/16/2012 | | DONE |
|
|
|
|