GCB-Final | 7/17/2012 | 7/18/2012 | 7/18/2012 | P | PASS |
Tom Arcoraci
|
|
|
David @ ###-#### PM Inspection struc final only
|
GCB-Energy | 5/31/2012 | 6/1/2012 | 6/1/2012 | P | PART |
Dave Hannah
|
|
|
David @ ###-#### Afternoon inspection requested ok to cover after gas piping passes
|
GCB-Energy | 5/30/2012 | 5/31/2012 | 5/31/2012 | A | PASS |
Jim Sly
|
|
|
David @ ###-#### Talked to David.........He still needs an inspection on gas pressure. Do not cover until pressure test passes.
|
GCB-Framing | 5/29/2012 | 5/30/2012 | 5/30/2012 | P | PASS |
Jim Sly
|
|
|
David @ ###-#### PM Inspection Note......OK to insulate when Gas pressure test approved. Noted this on blue sticker.
|
GCB-Shearwall | 5/22/2012 | 5/23/2012 | 5/23/2012 | A | PASS |
Dave Hannah
|
|
|
###-#### sheer walls and sheetrock soffits ok to cover
|
GCB-Shearwall | 5/18/2012 | 5/21/2012 | 5/21/2012 | A | PASS |
Dave Hannah
|
|
|
###-####
|
GCB-Fndatn/slab ins/fld vent | 5/2/2012 | 5/3/2012 | 5/3/2012 | A | PASS |
Tom Arcoraci
|
|
|
Bill @###-####
|
GCB-Footing | 4/30/2012 | 5/1/2012 | 5/1/2012 | A | PASS |
Tom Arcoraci
|
|
|
Bill @ ###-####
|
Plan assigned to (SRZ) | 4/6/2012 | 4/6/2012 | 4/24/2012 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Corrections are needed.
|
Routing - PLAN CHECK | 4/24/2012 | | 4/24/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 4/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 4/19/2012 | | |
Sam Zahorka
|
|
|
|
1st review completed | | | 4/13/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 4/9/2012 | | 4/13/2012 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 4/12/2012 | | 4/12/2012 | | PASS |
Troy James
|
|
|
|
Routing - Mechanical Review | 4/6/2012 | | 4/9/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Teds Heating
|
Application received | | | 4/5/2012 | | DONE |
|
|
|
|