GCB-Final | 7/3/2013 | 7/3/2013 | 7/3/2013 | P | PASS |
Tony Young
|
|
|
Dillon Phone #: ###-####
|
GCB-Final | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | NH |
Jim Sly
|
|
|
Dillon ###-#### No access......Called Dillon and left mssg.on his V/M. Left note at jobsite. No access.
|
GCB-Final | 6/26/2013 | 6/27/2013 | 6/28/2013 | P | FAIL |
Dave Hannah
|
|
|
Dillon ###-#### needs hand rail and fix step into garage
|
GCB-Fire Wall | 11/30/2012 | 12/3/2012 | 12/3/2012 | A | PASS |
Dave Hannah
|
|
|
Dylan @ ###-#### Firewall inspection for new townhome
|
GCB-Framing | 11/28/2012 | 11/29/2012 | 11/29/2012 | A | PART |
Tom Arcoraci
|
|
|
Dylan @ ###-#### ok to cover all but patch in fire wall
|
GCB-Energy | 11/29/2012 | 11/29/2012 | 11/29/2012 | A | PASS |
Tom Arcoraci
|
|
|
Dylan @ ###-####
|
GCB-Framing | 11/26/2012 | 11/27/2012 | 11/27/2012 | P | PART |
Tony Young
|
|
|
Dylan @ ###-#### PM Inspection,, correction posted,, ok to insulate
|
GCB-Shearwall | 11/1/2012 | 11/2/2012 | 11/2/2012 | A | PASS |
Tom Arcoraci
|
|
|
Dylan @ ###-####
|
GCB-Fire Wall | 9/20/2012 | 9/21/2012 | 9/21/2012 | A | PART |
Dave Hannah
|
|
|
Dylan @ ###-#### AM inspection requested first floor ok
|
GCB-Fndatn/slab ins/fld vent | 8/28/2012 | 8/28/2012 | 8/28/2012 | P | PASS |
Tony Young
|
|
|
Dylan @ ###-#### Townhome Project
|
GCB-Footing | 8/22/2012 | 8/23/2012 | 8/23/2012 | P | PASS |
Jim Sly
|
|
|
Dylan @ ###-#### PM Inspection
|
Plan assigned to (SRZ) | 8/21/2012 | 8/21/2012 | 8/22/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 8/21/2012 | | 8/22/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 8/22/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 8/21/2012 | | DONE |
Christina Prado
|
|
|
Received two copied sets of applications, manual j's, rescheck and three sets of plans marked CS, 1, 2, 3, 4, 5, 6, 7, 8, B, 9 & 10. Taken to Sam for additional review
|
Issue and Courier | | | 8/14/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 5/8/2012 | 5/8/2012 | 8/13/2012 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Corrections are needed.
2nd review completed. Corrections needed.
3rd review completed. Red-lined plans. Waiting for copies prior to issuance.
|
Routing - PLAN CHECK | 6/1/2012 | | 8/13/2012 | | PASS |
Sam Zahorka
|
|
|
Per red-lined plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2012 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 8/9/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the applicant and his designer. Discussed third plan review corrections and red-lined 1 set of plans to expedite plan review for them. Requested the designer to pick up plans and make two copies with red-lines.
|
Plan resubmittals received | | | 7/30/2012 | | |
|
|
|
Received 3 copies of sheets CS, 1, 2, 3, 4, 5, 6, 7, 8, B, 10 and taken to Sam Zahorka
|
Routing - PLAN CHECK | 5/31/2012 | | 6/1/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 5/31/2012 | | |
Barbara Stitt
|
|
|
|
1st review completed | | | 5/16/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/10/2012 | | 5/16/2012 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 5/11/2012 | | 5/11/2012 | | PASS |
Troy James
|
|
|
|
Routing - Mechanical Review | 5/8/2012 | | 5/10/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to A1 heating
|
Application received | | | 5/4/2012 | | DONE |
|
|
|
|