GCB-Final | 12/20/2012 | 12/21/2012 | 12/21/2012 | A | PASS |
Jim Storey
|
|
|
Nate @ ###-####
|
GCB-Final | 12/18/2012 | 12/19/2012 | 12/19/2012 | A | FAIL |
Jim Storey
|
|
|
Please call ahead wrong hardware back doors/ and ada restarooms.
|
GCB-Fire Wall | 12/11/2012 | 12/11/2012 | 12/11/2012 | P | PASS |
Jim Storey
|
|
|
Nate @ ###-#### Call in advance firewalls ok/ need to check firestopping/ papper insulation in ceilling is covered/ handrails/front windows. at final.
|
GCB-Fire Wall | 10/26/2012 | 10/29/2012 | 10/29/2012 | A | FAIL |
Jim Storey
|
|
|
Nate @ ###-#### resub mit to planreview to show and address common restarooms to maintain 2 hr protection.
|
GCB-Courtesy | 10/19/2012 | 10/22/2012 | 10/22/2012 | A | DONE |
Dave Hannah
|
|
|
Nate @ ###-#### Early AM Inspection - Call in advance talked about fire walls ok to use east wall
|
Plan assigned to (SRZ) | 5/22/2012 | 5/22/2012 | 10/9/2012 | | DONE |
Sam Zahorka
|
|
|
1st review completed 6/4/12. Corrections are needed.
2nd Review complete. Pending Mechanical to pass prior to issuance.
|
Routing - PLAN CHECK | 10/9/2012 | | 10/9/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/9/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 10/3/2012 | | 10/4/2012 | | FAIL |
Sam Zahorka
|
|
|
Need structural evaluation of the existing roof systems ability to carry the new RTU.
|
Telephone call | | | 10/4/2012 | | DONE |
Sam Zahorka
|
|
|
Called the architect. No answer. Need structural evaluation of the existing roof system to carry the new RTU.
|
Routing - Mechanical Review | 9/28/2012 | | 10/3/2012 | | PASS |
Troy James
|
|
|
|
Plan resubmittals requested | | | 9/28/2012 | | DONE |
Christina Prado
|
|
|
Received three sets of plans marked M1.0 & M2.0; routed to Sam Zahorka for review
|
Routing - PLAN CHECK | 8/22/2012 | | 9/28/2012 | | PEND |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 8/22/2012 | | 8/23/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Leon Letson with Garden City
|
Routing - PLAN CHECK | 8/16/2012 | | 8/23/2012 | | PEND |
Sam Zahorka
|
|
|
Pending Mechanical to PASS. Building review is PASSED per red-lines.
|
Plan resubmittals received | | | 8/22/2012 | | |
|
|
|
Recieved 3 copies of response letter dated 8-13-12from George Slaughter, 3 copies of Lighting compliance, 3 copies of sheets A2, A3, A4 and taken to Sam Zahorka//BAS
|
Plan resubmittals received | | | 8/16/2012 | | |
|
|
|
Received 3 copies of the Title sheet, Floor plan/Demolition plan, Details and taken to Sam Zahora's desk
|
Meeting | | | 8/8/2012 | | DONE |
Sam Zahorka
|
|
|
Meeting to discuss the Mechanical Ventalation and exhaust requirements at Garden City hall with the applicant, his architect and Mechanical engineer, Bill Vandegraft, Troy James, Leon, and myself. Discussed possible solutions or avenues to achieve approvals. Waiting for re-submittal corrections from 1st building and mechanical reviews.
|
Meeting | | | 7/18/2012 | | DONE |
Sam Zahorka
|
|
|
Meeting held with the Building Official, Plumbing/Mechanical Supervisor, Mechanical Plan Reviewer, and myself. Discussed this tenants corrections concerning the Mechanical requirements for its proposed use. Responded to Garden City in email on how to proceed with the Design Professionals request for possible request for appeals.
|
Routing - Mechanical Review | 7/9/2012 | | 7/9/2012 | | FAIL |
Troy James
|
|
|
reviewed letter sent by architect, no resubmitted plans
|
Plan resubmittals requested | | | 7/5/2012 | | DONE |
Christina Prado
|
|
|
received one response letter addressed to Troy James & Leon Letson as well as two sheet of mechanical information. Gave to Troy and e-mailed copy to Leon at Garden City
|
Routing - PLAN CHECK | 5/24/2012 | | 6/4/2012 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
1st review completed | | | 6/4/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 5/22/2012 | | 5/24/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to Leon
|
Application received | | | 5/15/2012 | | DONE |
|
|
|
|