GCB-Final | 11/30/2012 | 11/30/2012 | 11/30/2012 | P | PASS |
Tony Young
|
|
|
John @ ###-####,,, structural final ok
|
GCB-Final | 11/29/2012 | 11/30/2012 | 11/30/2012 | A | FAIL |
Tony Young
|
|
|
John @ ###-####,, not ready,, I re-scheduled for pm at contractors request
|
GCB-Final | 11/28/2012 | 11/29/2012 | 11/29/2012 | A | FAIL |
Tom Arcoraci
|
|
|
John @ ###-#### needs tempered glazing in master bedroom windows at door or other approved material
|
GCB-Framing | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | CANC |
Mike Jordan
|
|
|
Kevin @ ###-####
|
GCB-Energy | 8/22/2012 | 8/23/2012 | 8/23/2012 | A | PASS |
Mike Jordan
|
|
|
Kevin @ ###-####
|
GCB-Framing | 8/20/2012 | 8/21/2012 | 8/21/2012 | A | PASS |
Jim Sly
|
|
|
Kevin @ ###-####
|
GCB-Stem wall | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PASS |
Tony Young
|
|
|
Westley @ ###-#### AM inspection requested,, reae porch wall ok
|
GCB-Fndatn/slab ins/fld vent | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | PASS |
Tony Young
|
|
|
Westley @ ###-#### AM inspection requested,, patio foundation ok
|
Plan assigned to (SRZ) | | 7/11/2012 | 7/12/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 7/11/2012 | | 7/12/2012 | | PASS |
Sam Zahorka
|
|
|
Plan Mod
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 7/12/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - Mechanical Review | 7/11/2012 | | 7/11/2012 | | PASS |
Troy James
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 6/22/2012 | 6/25/2012 | 6/25/2012 | P | PART |
Mike Jordan
|
|
|
Ryan @ ###-#### PM Inspection
|
GCB-Footing | 6/21/2012 | 6/22/2012 | 6/22/2012 | P | PASS |
Dave Hannah
|
|
|
Ryan @ ###-#### PM Inspection
|
Plan assigned to (SRZ) | 6/11/2012 | 6/11/2012 | 6/18/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/12/2012 | | 6/18/2012 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
1st review completed | | | 6/18/2012 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 6/18/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Mechanical Review | 6/11/2012 | | 6/12/2012 | | PASS |
Troy James
|
|
|
|
Application received | | | 6/8/2012 | | DONE |
|
|
|
|