GCB-Final | 1/24/2013 | 1/25/2013 | 1/25/2013 | A | PASS |
Tom Arcoraci
|
|
|
Marty ###-#### building final ok
|
GCB-Energy | 11/26/2012 | 11/27/2012 | 11/27/2012 | A | PASS |
Mike Jordan
|
|
|
Marty @ ###-####
|
GCB-Energy | 11/19/2012 | 11/20/2012 | 11/20/2012 | A | PART |
Jim Sly
|
|
|
Marty @ ###-#### Late A.M. - CHANGED from energycode insp to Frame insp. Notified owner of option....3rd party air seal insp or blower door. Framing Pass.
|
GCB-Energy | 11/16/2012 | 11/19/2012 | 11/19/2012 | P | CANC |
Dave Hannah
|
|
|
Marty @ ###-#### PM Inspection Inspection cancelled from web by: Barbara Stitt
|
GCB-Shearwall | 10/25/2012 | 10/26/2012 | 10/26/2012 | A | PASS |
Mike Jordan
|
|
|
Marty @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 9/24/2012 | 9/25/2012 | 9/25/2012 | A | PASS |
Mike Jordan
|
|
|
Marty @ ###-#### Call in advance
|
GCB-Footing | 9/17/2012 | 9/18/2012 | 9/18/2012 | A | PASS |
Jim Sly
|
|
|
Marty @ ###-#### Call in advance
|
Plan assigned to (SRZ) | | 8/6/2012 | 8/30/2012 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Correctinos needed.
|
Routing - PLAN CHECK | 8/30/2012 | | 8/30/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 8/30/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 8/29/2012 | | |
|
|
|
Received 3 copies of Sheets S2.00, S2.01, A2.01 and taken to Sam Zahorka
|
Telephone call | | | 8/21/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the architect. Discussed needed corrections and plan review report. Emailed plan review report to him.
|
Routing - PLAN CHECK | 8/7/2012 | | 8/17/2012 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 8/16/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 8/6/2012 | | 8/7/2012 | | PASS |
Troy James
|
|
|
|
Application received | | | 8/2/2012 | | DONE |
|
|
|
|