GCB-Final | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | PASS |
Jim Sly
|
|
|
Goldy ###-#### Sructural final only.......OK.
|
GCB-Final | 3/6/2013 | 3/7/2013 | 3/7/2013 | A | FAIL |
Jim Sly
|
|
|
Goldy @ ###-#### Call in advance Handrail return, Verification from Leon on exactly what is required for off street parking, sidewalk, walkway. Need Electr and Plumbing finals.
|
GCB-Energy | 1/8/2013 | 1/9/2013 | 1/9/2013 | P | PASS |
Dave Hannah
|
|
|
Goldy @ ###-#### PM Inspection
|
GCB-Framing | 11/5/2012 | 11/6/2012 | 11/7/2012 | P | PASS |
Dave Hannah
|
|
|
Goldy @ ###-#### ok to insulate but still needs mec rough in
|
GCB-Courtesy | 9/21/2012 | 9/24/2012 | 9/24/2012 | A | DONE |
Dave Hannah
|
|
|
Goldy @ ###-#### Framing Conference request
|
GCB-Fndatn/slab ins/fld vent | 9/6/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Jim Sly
|
|
|
Goldy @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 9/5/2012 | 9/5/2012 | 9/5/2012 | P | NR |
Dave Hannah
|
|
|
Goldy @ ###-####
|
GCB-Footing | 9/5/2012 | 9/5/2012 | 9/5/2012 | P | PASS |
Dave Hannah
|
|
|
Goldy @ ###-####
|
Issue and Courier | | | 8/24/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 8/6/2012 | 8/6/2012 | 8/23/2012 | | DONE |
Sam Zahorka
|
|
|
Pending Mechanical to PASS
|
Routing - Mechanical Review | 8/23/2012 | | 8/23/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/23/2012 | | 8/23/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 8/7/2012 | | 8/17/2012 | | PEND |
Sam Zahorka
|
|
|
Pending Mechanical PASS
|
1st review completed | | | 8/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (REV) | | | 8/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 8/6/2012 | | 8/7/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to western heating
|
Application received | | | 8/3/2012 | | DONE |
|
|
|
|