GCB-Final | 1/23/2013 | 1/24/2013 | 1/24/2013 | A | PASS |
Jim Sly
|
|
|
###-#### Call for access
|
GCB-Final | 1/18/2013 | 1/18/2013 | 1/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
John @ ###-#### building final is ok 408
|
GCB-Energy | 11/13/2012 | 11/13/2012 | 11/13/2012 | P | PASS |
Jim Sly
|
|
|
John @ ###-####
|
GCB-Framing | 11/8/2012 | 11/9/2012 | 11/9/2012 | A | PASS |
Tom Arcoraci
|
|
|
John @ ###-####
|
GCB-Shearwall | 10/24/2012 | 10/25/2012 | 10/25/2012 | P | PASS |
Mike Jordan
|
|
|
John @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 9/28/2012 | 10/1/2012 | 10/1/2012 | A | PASS |
Dave Hannah
|
|
|
|
GCB-Footing | 9/28/2012 | 9/28/2012 | 9/28/2012 | P | PASS |
Jim Sly
|
|
|
|
GCB-Footing | 9/27/2012 | 9/27/2012 | 9/27/2012 | P | NR |
Mike Jordan
|
|
|
Adam @ ###-####. no one on site. no forms were construcuted.
|
Plan assigned to (SRZ) | 8/17/2012 | 8/17/2012 | 8/30/2012 | | DONE |
Sam Zahorka
|
|
|
1st review complete. Pending Mechanical to PASS.
|
Routing - Mechanical Review | 8/30/2012 | | 8/30/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/30/2012 | | 8/30/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 8/30/2012 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 8/17/2012 | | 8/28/2012 | | PEND |
Sam Zahorka
|
|
|
Pending Mechanical to Pass.
|
Routing - Mechanical Review | 8/17/2012 | | 8/17/2012 | | FAIL |
Troy James
|
|
|
emailed correction to Western Heating
|
Application received | | | 8/15/2012 | | DONE |
|
|
|
|