GCB-Final | 12/3/2012 | 12/4/2012 | 12/4/2012 | A | PASS |
Mike Jordan
|
|
|
Chi @ ###-#### Call for access. structural final only ok. no card to sign.
|
GCB-Energy | 10/24/2012 | 10/25/2012 | 10/25/2012 | P | PASS |
Mike Jordan
|
|
|
Chi @ ###-#### PM Inspection
|
GCB-Framing | 10/23/2012 | 10/24/2012 | 10/24/2012 | A | PASS |
Mike Jordan
|
|
|
Chi @ ###-####
|
GCB-Energy | 10/16/2012 | 10/17/2012 | 10/17/2012 | A | PART |
Jim Sly
|
|
|
Chi @ ###-#### Call in advance This should have been and inspection of fire rated soffits on West side of structure. This has been completed.
|
GCB-Shearwall | 10/12/2012 | 10/15/2012 | 10/15/2012 | P | PASS |
Jim Sly
|
|
|
Chi @ ###-####
|
GCB-Fndatn/slab ins/fld vent | 9/19/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Dave Hannah
|
|
|
Chris @ ###-#### AM inspection requested.
|
GCB-Framing | 9/18/2012 | 9/19/2012 | 9/20/2012 | P | CANC |
Dave Hannah
|
|
|
###-#### 3:30 PM inspection requested.
|
GCB-Footing | 9/20/2012 | 9/20/2012 | 9/20/2012 | A | PASS |
Dave Hannah
|
|
|
|
Plan assigned to (SRZ) | 8/28/2012 | 8/28/2012 | 9/17/2012 | | DONE |
Sam Zahorka
|
|
|
Failed 1st review. Waiting for corrections.
|
Routing - PLAN CHECK | 9/7/2012 | | 9/17/2012 | | PASS |
Sam Zahorka
|
|
|
Samm Zahorka
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 9/17/2012 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 9/7/2012 | | |
|
|
|
Received 3 sets of plans and routed to Sam Zahorka
|
1st review completed | | | 9/4/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 8/30/2012 | | 9/4/2012 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 8/31/2012 | | 8/31/2012 | | PASS |
Troy James
|
|
|
|
Routing - Mechanical Review | 8/28/2012 | | 8/30/2012 | | FAIL |
Troy James
|
|
|
emailed corrections to designer and Garden City
|
Application received | | | 8/24/2012 | | DONE |
Barbara Stitt
|
|
|
|