GCB-Final | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PASS |
Mike Jordan
|
|
|
Robert ###-#### call first. Structural final only ok.
|
GCB-Framing | 9/4/2013 | 9/4/2013 | 9/4/2013 | P | PASS |
Mike Jordan
|
|
|
Dave ###-####. North and south canopy framing and heavy timber ok.
|
GCB-Framing | 8/12/2013 | 8/13/2013 | 8/13/2013 | A | PASS |
Mike Jordan
|
|
|
Terry ###-####. Steel stud framing for new storefront, south half.
|
GCB-Framing | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | NH |
Jim Storey
|
|
|
Terry ###-#### no one on site no plans defrered to am 8/13
|
GCB-Framing | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | PART |
Dave Hannah
|
|
|
Dave ###-#### Partial framing north half on to cover
|
GCB-Framing | 6/20/2013 | 6/21/2013 | 6/21/2013 | A | CANC |
Mike Jordan
|
|
|
###-#### Partial framing. Per contractor, this inspection was schedule for monday in the am , not today. Noted to contractor to contact garden city to reschedule for monday in the am.
|
GCB-Framing | 6/13/2013 | 6/14/2013 | 6/18/2013 | A | PART |
Dave Hannah
|
|
|
Dan ###-#### Partial framing inspect for exterior cover ok to cover north section
|
GCB-Footing | 2/19/2013 | 2/20/2013 | 2/20/2013 | P | PASS |
Tony Young
|
|
|
DAN ###-####,, pier footings on north side of enterance ok per new engineering
|
GCB-Footing | 2/15/2013 | 2/6/2013 | 2/15/2013 | A | DONE |
Dave Hannah
|
|
|
DAVE ###-#### AS CLOSE TO 2PM AS POSSIBLE PLEASE; PLAN TO POUR AT 3PM
|
GCB-Footing | 2/6/2013 | 2/6/2013 | 2/7/2013 | P | PART |
Dave Hannah
|
|
|
Dave @###-#### four column ftgs south end ok to place concrete.
|
Plan assigned to (SRZ) | 9/27/2012 | 9/27/2012 | 10/10/2012 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Pending COMcheck submittal from architect for exterior lighting compliance.
|
Routing - PLAN CHECK | 10/9/2012 | | 10/10/2012 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2012 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/10/2012 | | DONE |
Barbara Stitt
|
|
|
|
1st review completed | | | 10/9/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/27/2012 | | 10/9/2012 | | PEND |
Sam Zahorka
|
|
|
Pending COMcheck for exterior lighting compliance.
|
Application received | | | 9/25/2012 | | DONE |
|
|
|
|