GCB-Final | 11/27/2013 | 12/2/2013 | 12/2/2013 | A | PASS |
Jim Sly
|
|
|
Dan ###-#### call for garage code access Struct insp only....OK.
|
GCB-Energy | 4/29/2013 | 4/29/2013 | 4/30/2013 | P | PASS |
Dave Hannah
|
|
|
Dan ###-####
|
GCB-Framing | 4/26/2013 | 4/26/2013 | 4/26/2013 | P | PASS |
Jim Sly
|
|
|
Dan @ ###-#### Please inform GC Staff if any re-inspection fees should be applied to this project
|
GCB-Framing | 4/25/2013 | 4/25/2013 | 4/25/2013 | P | NR |
Jim Sly
|
|
|
Dan @ ###-#### Complete corrections
|
GCB-Framing | 4/24/2013 | 4/24/2013 | 4/24/2013 | A | DEFR |
Dave Hannah
|
|
|
Dan ###-####
|
GCB-Framing | 4/24/2013 | 4/24/2013 | 4/24/2013 | P | FAIL |
Mike Jordan
|
|
|
Dan Phone #: ###-####. 2Hr. firewall to be continous to bottom side of roof deck, north side. Provide 2 layers of 5/8 type x rock at all soffits on 2 hr. wall. Complete all fireblocking at chases, ducts plumbing and furrwed out walls.Provide laydown parapet at south wall 1st. floor, repair laydown parapet were penetrated. Follow point load from beam upstairs. Correction notice posted. do not cover.
|
GCB-Fire Wall | 4/15/2013 | 4/15/2013 | 4/15/2013 | P | PASS |
Mike Jordan
|
|
|
Dan @ ###-#### 1st Layer of Drywall Call in advance. BAse layer ok.
|
GCB-Fire Wall | 4/12/2013 | 4/15/2013 | 4/15/2013 | A | PART |
Mike Jordan
|
|
|
Dan @ ###-####. Ok to to install first layer of 5/8 type x rock on this unit only. Needs to remove foam seal from top plate electrical wire penetrations and fill with an approved intumesant caulking.
|
GCB-Shearwall | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Mike Jordan
|
|
|
Dan ###-####. Exterior wall bracing ok. This is for both units, 448 and 454. Contractor needs to start calling in both permits for inspections.
|
GCB-Fire Wall | 4/5/2013 | 4/8/2013 | 4/8/2013 | A | PASS |
Mike Jordan
|
|
|
Dan @ ###-#### Call in advance. Ok for 1st. layer of 5/8 type x.
|
GCB-Shearwall | 4/5/2013 | 4/8/2013 | 4/8/2013 | A | FAIL |
Mike Jordan
|
|
|
Dan @ ###-#### Call in advance. Noted several areas were staples are overdriven or missing. areas marked on wall.
|
Plan assigned to (SRZ) | 4/3/2013 | 4/3/2013 | 4/3/2013 | | DONE |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - PLAN CHECK | 4/3/2013 | | 4/3/2013 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2013 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/3/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 4/3/2013 | | |
|
|
|
Plan modification-recieved 3 copies of Structural calcualtions for fire wall revisions, 3 sheets-beams supporting proposed bearing in fire wall all taken to Sam Zahorka's office
|
GCB-Fire Wall | 3/29/2013 | 4/1/2013 | 4/1/2013 | P | DONE |
Mike Jordan
|
|
|
Dan @ ###-#### Call in advance. Conferance with builder. Needs to submit fixes for approval. Also went over continuity issues on 2 hr. firewall and penetrations in laydown parapet that need to be removed.
|
GCB-Framing | 3/29/2013 | 3/29/2013 | 3/29/2013 | P | FAIL |
Mike Jordan
|
|
|
Dan @ ###-####. No approved plans on site. Per Sam still needs to submit corrections for approval.
|
Meeting | | | 3/19/2013 | | DONE |
Sam Zahorka
|
|
|
Meeting with Dan French and his engineer/designer Shawn Reeder. Discussed how to fix the penetrations and continuity of the 2 hour townhouse separation walls. Offered solutions and requested engineering for the new column and footing locations. Also requested additional information about the continuity of the townhouse wall above the ceiling line to the roof deck. Shawn stated he would resubmit these correction items to plan review.
|
GCB-Footing | 2/15/2013 | 2/14/2013 | 2/19/2013 | P | DONE |
Dave Hannah
|
|
|
Heron @ ###-#### PM Inspection
|
GCB-Footing | 2/15/2013 | 2/15/2013 | 2/15/2013 | P | PASS |
Jim Sly
|
|
|
Huron Ready at 3:30 Phone #: ###-####
|
GCB-Footing | 2/14/2013 | 2/14/2013 | 2/14/2013 | P | CANC |
Jim Sly
|
|
|
Heron @ ###-#### Contr.cancelled.
|
Plan assigned to (SRZ) | 11/20/2012 | 11/20/2012 | 1/18/2013 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - PLAN CHECK | 1/14/2013 | | 1/18/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2013 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 1/18/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 1/11/2013 | | DONE |
Christina Prado
|
|
|
Received three sets of plans marked A1.3, S1.0, S1.2, S5.0, E1.0 & three sheets with no label as well as three sets new REScheck & wall bracing calcs; routed to Sam for additional review
|
Meeting | | | 12/7/2012 | | DONE |
Sam Zahorka
|
|
|
Met with the applicant. explained needed corrections items. Requested he hire a designer or engineer to assist him with correcting the drawings.
|
Plan resubmittals requested | | | 12/7/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke with the applicants engineer/designer. explained corrections and typed up an itemized report. emailed corrections to Garden City and the engineer.
|
Routing - PLAN CHECK | 12/7/2012 | | 12/7/2012 | | FAIL |
Sam Zahorka
|
|
|
|
Telephone call | | | 12/7/2012 | | DONE |
Sam Zahorka
|
|
|
Spoke to the applicant and his engineer/designer. Requested corrections.
|
Routing - PLAN CHECK | 11/21/2012 | | 12/4/2012 | | FAIL |
Sam Zahorka
|
|
|
Incomplete submittals.
|
1st review completed | | | 12/4/2012 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 11/20/2012 | | 11/21/2012 | | PASS |
Troy James
|
|
|
|
Application received | | | 11/16/2012 | | DONE |
|
|
|
|