Permit Information
Permit NumberGCB12-00154
StatusFinaled
Name French Homes Inc.
Site Address 454 E 51ST
Project NameBLD2012-00154
Customer Number 
ePlanReviewNo
Description
(Lot 6 Townhome) - To construct a new 1,369 square foot two story, (554 square foot 1st Story / 815 square foot 2nd Story), three bedroom, two and a half bathroom, single family dwelling townhouse with a 406 square foot attached two car garage, and a 40 square foot covered front porch, and a 48 square foot covered rear patio. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. This lot is within a Floodplain area. The elevation certificate is attached to the approved plans. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final6/6/20136/6/20136/6/2013PPASS
DetailsDave Hannah
Dan Phone #: ###-####
GCB-Final6/4/20136/5/20136/5/2013PFAIL
DetailsMike Jordan
Dan Phone #: ###-####. Provide blower door test results and post or the 3rd party airseal inspection report. Provide the approved energy cert and post. Remove roof vent from 4ft. laydown parapet and repair. Correction notice posted.
GCB-Energy4/29/20134/29/20134/30/2013PPASS
DetailsDave Hannah
Dan ###-####
GCB-Framing4/26/20134/26/20134/26/2013PPASS
DetailsJim Sly
Dan @ ###-####
Please inform GC Staff if any re-inspection fees should be applied to this project
GCB-Framing4/25/20134/25/20134/25/2013PPART
DetailsJim Sly
Dan @ ###-####
OK to insulate......Need post in Gar.......point load from beam above. Need small pc. of rock at 2hr wall overbuild Garage.
GCB-Framing4/24/20134/24/20134/24/2013ADEFR
DetailsDave Hannah
Dan ###-####
GCB-Fire Wall4/24/20134/24/20134/24/2013ADEFR
DetailsDave Hannah
Dan ###-####
GCB-Framing4/24/20134/24/20134/24/2013PNR
DetailsMike Jordan
Dan Phone #: ###-####. no mech. ri inspection.
GCB-Fire Wall4/24/20134/24/20134/24/2013PPASS
DetailsMike Jordan
Dan Phone #: ###-####
Plan assigned to (SRZ)4/3/20134/3/20134/3/2013 DONE
DetailsSam Zahorka
Sam Zahorka
Routing - PLAN CHECK4/3/2013 4/3/2013 PASS
DetailsSam Zahorka
Sam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  4/3/2013 DONE
DetailsSam Zahorka
CHANGE STATUS TO (ISS)  4/3/2013 DONE
DetailsBarbara Stitt
Plan resubmittals received  4/3/2013  
Plan modification-recieved 3 copies of Structural calcualtions for fire wall revisions, 3 sheets-beams supporting proposed bearing in fire wall all taken to Sam Zahorka's office
GCB-Courtesy3/18/20133/19/20133/19/2013APART
DetailsTom Arcoraci
Dan French @ ###-#### 2 hour wall issues sent to plan review
Meeting  3/19/2013 DONE
DetailsSam Zahorka
Meeting with Dan French and his engineer/designer Shawn Reeder. Discussed how to fix the penetrations and continuity of the 2 hour townhouse separation walls. Offered solutions and requested engineering for the new column and footing locations. Also requested additional information about the continuity of the townhouse wall above the ceiling line to the roof deck. Shawn stated he would resubmit these correction items to plan review.
GCB-Footing2/15/20132/14/20132/19/2013PDONE
DetailsDave Hannah
Heron @ ###-####
PM Inspection
GCB-Footing2/15/20132/15/20132/15/2013PPASS
DetailsJim Sly
Huron-Ready at 3:30 Phone #: ###-####
GCB-Footing2/14/20132/14/20132/14/2013PCANC
DetailsJim Sly
Heron @ ###-####
Contr. Cancelled.
Plan assigned to (SRZ)11/20/201211/20/20121/18/2013 DONE
DetailsSam Zahorka
1st review completed.
Routing - PLAN CHECK1/14/2013 1/18/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  1/18/2013 DONE
DetailsSam Zahorka
Issue and Courier  1/18/2013 DONE
DetailsBarbara Stitt
Plan resubmittals received  1/11/2013 DONE
DetailsChristina Prado
Received three sets of plans marked A1.3, S1.0, S1.2, S5.0, E1.0 & three sheets with no label as well as three sets new REScheck & wall bracing calcs; routed to Sam for additional review
Routing - PLAN CHECK12/7/2012 12/7/2012 FAIL
DetailsSam Zahorka
Plan resubmittals requested  12/7/2012 DONE
DetailsSam Zahorka
Spoke with the applicants engineer/designer. explained corrections and typed up an itemized report. emailed corrections to Garden City and the engineer.
Meeting  12/7/2012 DONE
DetailsSam Zahorka
Met with the applicant. explained needed corrections items. Requested he hire a designer or engineer to assist him with correcting the drawings.
Telephone call  12/7/2012 DONE
DetailsSam Zahorka
Spoke to the applicant and his engineer/designer. Requested corrections.
Routing - PLAN CHECK11/21/2012 12/4/2012 FAIL
DetailsSam Zahorka
Incomplete submittals.
1st review completed  12/4/2012 DONE
DetailsSam Zahorka
Routing - Mechanical Review11/20/2012 11/21/2012 PASS
DetailsTroy James
Application received  11/16/2012 DONE