GCB-Final | 9/18/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Jim Sly
|
|
|
Julio ###-####
|
GCB-Final | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | PART |
Jim Sly
|
|
|
Julio ###-#### OK for Temp Occ. OK for Perm Occ when all other agencies are approved for Perm Occ.
|
GCB-Final | 9/16/2014 | 9/16/2014 | 9/16/2014 | P | PEND |
Jim Sly
|
|
|
Julio ###-#### Walk thru
|
GCB-Framing | 9/15/2014 | 9/15/2014 | 9/15/2014 | P | PASS |
Dave Hannah
|
|
|
Julio ###-#### canopy framing inspectino request
|
GCB-Ceiling Grid | 9/4/2014 | 9/5/2014 | 9/5/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Select ceiling grid OK.
|
GCB-Framing | 8/14/2014 | 8/15/2014 | 8/15/2014 | A | PART |
Jim Sly
|
|
|
###-#### Julio Verified installation of Tenmat FF109X fire rated light covers above can lights. Product approved by Sam Zahorka plan check.
|
GCB-Framing | 7/31/2014 | 8/1/2014 | 8/1/2014 | A | CANC |
Jim Sly
|
|
|
|
GCB-Framing | 7/21/2014 | 7/22/2014 | 7/22/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-####
|
GCB-Framing | 7/10/2014 | 7/11/2014 | 7/11/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### Completes all framing insp.
|
Plan assigned to (SRZ) | 7/10/2014 | 7/10/2014 | 7/11/2014 | | DONE |
Sam Zahorka
|
|
|
Grace Plan Mod for Mechanical
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 7/10/2014 | | 7/11/2014 | | PASS |
Sam Zahorka
|
|
|
Plan modification processing
|
CHANGE STATUS TO (ISS) | | | 7/11/2014 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 7/10/2014 | | DONE |
Sam Zahorka
|
|
|
provided clarification to duct/air transfer penetration openings over the telephone to a gentleman named Robin which is the mechanical contractor for this job. I explained when the roof/ceiling assembly transitions from 9 feet to 12 feet you’ll need to add dampers wherever the ducts penetrate the 1-hour ceiling, whether it’s a horizontal membrane or a vertical membrane. If the assembly transitions vertical, add sheetrock to the attic truss matching the rating (sheetrock layers) of the 1-hour roof ceiling assembly and still add a damper.
|
CHANGE STATUS TO (REV) | | | 7/10/2014 | | |
Sam Zahorka
|
|
|
Plan modifications for Mechanical Received.
|
Routing - Mechanical Review | 7/10/2014 | | 7/10/2014 | | PASS |
Troy James
|
|
|
Plan modifications for mechanical sheets
|
Plan resubmittals received | | | 7/9/2014 | | |
|
|
|
Received 2 copies of sheets M1.2, M2.2, M4.1 and taken to Sam Zahorka
|
GCB-Framing | 7/7/2014 | 7/8/2014 | 7/8/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Conf.
|
GCB-Framing | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PART |
Mike Jordan
|
|
|
Julio ###-####. Framing at northwest qudrant and front canopy. Needs to install roll blocking on trusses at interior bearing wall locations. also discussed plan for can lights in rated roof/ceiling assemblies.
|
GCB-Framing | 6/20/2014 | 6/23/2014 | 6/23/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### Rooms only......2hr wall to West exterior wall.
|
GCB-Framing | 6/17/2014 | 6/20/2014 | 6/20/2014 | A | CANC |
Mike Jordan
|
|
|
Julio ###-####. Inspection cancelled.
|
GCB-Framing | 6/16/2014 | 6/16/2014 | 6/16/2014 | P | CANC |
Mike Jordan
|
|
|
Julio ###-####. Per phone call from julio, inscpection was cancelled.
|
GCB-Framing | 6/10/2014 | 6/12/2014 | 6/12/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### Framing insp ....far West wing OK C/N No openings within 4' 2hr wall, Non rated can lights in rated ceiling. Method to close 1/2" gap at top of walls with hat channel, provide fire/smoke dampers at make up air...Hood.
|
GCB-Framing | 6/6/2014 | 6/9/2014 | 6/9/2014 | P | PART |
Jim Sly
|
|
|
Julio ###-#### Select Areas.
|
GCB-Energy | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### spoke with Jim Sly about this inspection Sect 1.....OK
|
GCB-Fire Wall | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### spoke with Jim Sly about this inspection #2 2hr wall OK.
|
GCB-Framing | 6/4/2014 | 6/6/2014 | 6/6/2014 | A | PART |
Jim Sly
|
|
|
Julio Area 2.......OK
|
GCB-Energy | 6/4/2014 | 6/4/2014 | 6/4/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### 2hr wall to East end of bldg.
|
GCB-Assembly | 6/2/2014 | 6/4/2014 | 6/4/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### roof sheeting inspection requested Select roof nailing.
|
GCB-Fire Wall | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Jim Sly
|
|
|
Julio ###-#### Rooms only .........Framing and Firestopping OK far East wing......up to 2 hr wall
|
GCB-Fire Wall | 5/30/2014 | 6/2/2014 | 6/2/2014 | A | NR |
Jim Sly
|
|
|
Julio ###-#### for a firestop
|
GCB-Assembly | 5/29/2014 | 6/2/2014 | 6/2/2014 | A | PASS |
Jim Sly
|
|
|
Julio ###-#### roof and wall sheeting (?) inspection requested N and W walls OK Roof OK
|
GCB-Fire Wall | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | DONE |
Jim Sly
|
|
|
Julio ###-#### Conference on Firestopping.
|
GCB-Assembly | 5/28/2014 | 5/29/2014 | 5/29/2014 | A | PART |
Mike Jordan
|
|
|
FIRE STOPS OTHER JULIO ###-####. SWork in progress on firestopping at area 1. Double layer 5/8 type x being installed in concelled areas behind tub and pex is being firecaulked. Electrical not yet started. K2 to call for additional inspection whwn area 1 is completed.
|
GCB-Framing | 5/23/2014 | 5/27/2014 | 5/27/2014 | A | PART |
Jim Sly
|
|
|
Julio Framing OK 2 East wings..... Need firestopping and listings. Do not insulate.
|
GCB-Assembly | 5/21/2014 | 5/23/2014 | 5/23/2014 | A | PART |
Tony Young
|
|
|
Julio ###-#### roof sheet/structural inspection request roof nailing ok
|
GCB-Shearwall | 5/6/2014 | 5/7/2014 | 5/7/2014 | A | PASS |
Mike Jordan
|
|
|
Julio ###-####. Exterior shear walls, north east portion and courtyards 1 and 2.
|
GCB-Framing | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PART |
Tom Arcoraci
|
|
|
Julio ###-#### roof framing/roof sheathing inspection requeste wip ok
|
GCB-Assembly | 4/24/2014 | 4/25/2014 | 4/25/2014 | A | PART |
Jim Sly
|
|
|
Julio ###-#### roof nailing inspection request Section N. of Courtyard #3.....OK Circled on plan sheet.
|
GCB-Assembly | 4/21/2014 | 4/22/2014 | 4/22/2014 | P | NR |
Jim Sly
|
|
|
Herb ###-#### roof nailing inspection request; partial No access.
|
GCB-Assembly | 4/15/2014 | 4/16/2014 | 4/17/2014 | A | PART |
Dave Hannah
|
|
|
Herb ###-#### roof nailing inspection ok to cover see area marked on plans
|
GCB-Assembly | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | NR |
Jim Sly
|
|
|
Roof nailing.
|
GCB-Assembly | 4/11/2014 | 4/14/2014 | 4/14/2014 | A | CANC |
Jim Sly
|
|
|
Herb ###-#### roof nailing inspection
|
GCB-Assembly | 4/7/2014 | 4/8/2014 | 4/8/2014 | A | PART |
Tony Young
|
|
|
Herb ###-#### roof nailing inspection request Grace Assitsted Living,, far east wing ok
|
Plan assigned to (SRZ) | 1/6/2014 | 1/6/2014 | 1/8/2014 | | DONE |
Sam Zahorka
|
|
|
Carport has own BLD. See BLD2###-####2
|
CHANGE STATUS TO (ISS) | | | 1/8/2014 | | DONE |
Sam Zahorka
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 12/27/2013 | 12/30/2013 | 12/30/2013 | A | PASS |
Dave Hannah
|
|
|
Herb ###-#### Pour at 10:30 am
|
Plan resubmittals received | | | 12/27/2013 | | |
|
|
|
Received 4 copies of structural calcs for single-post carport, 4 copies of site plan, 4 copies of design calcs from Tim Covert P.E. Structural Engineer for Steelport Single-post Carport and taken to Sam's desk
|
GCB-Footing | 12/23/2013 | 12/24/2013 | 12/26/2013 | A | PART |
Dave Hannah
|
|
|
Herb ###-#### pouring at 9:30 am forms up and horz rebar in ground was coverd so there is no frost ok to place concrete
|
Routing - PLAN CHECK | 12/26/2013 | | 12/26/2013 | | PASS |
Sam Zahorka
|
|
|
Verified Garden City Plan Mod set was identical to plan mod set approved on 11/26/13. Provided approved stamp and signature. Routed back to Garden City.
|
GCB-Footing | 12/20/2013 | 12/20/2013 | 12/20/2013 | P | DEFR |
Mike Jordan
|
|
|
Herb ###-#### (1:30 pour). Pending special inspection.
|
GCB-Fndatn/slab ins/fld vent | 12/17/2013 | 12/18/2013 | 12/18/2013 | P | PART |
Mike Jordan
|
|
|
Herb ###-#### Foundation pour at 1:30. Spoke therb. concrete has been placed. special inspector on site.
|
GCB-Fndatn/slab ins/fld vent | 12/16/2013 | 12/17/2013 | 12/18/2013 | P | PART |
Jim Sly
|
|
|
Herb ###-#### pour at 1:30 special inspection provided Select walls at NE and SE sect. OK pend. Geotech special inspections, tests and approvals.
|
GCB-Fndatn/slab ins/fld vent | 12/12/2013 | 12/13/2013 | 12/13/2013 | A | PART |
Tom Arcoraci
|
|
|
Herb ###-#### pouring concrete at noon spec inspector on site
|
Plan assigned to (SRZ) | 12/13/2013 | 12/13/2013 | 12/13/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 12/13/2013 | | 12/13/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/13/2013 | | DONE |
Barbara Stitt
|
|
|
Issue plan modification
|
Plan resubmittals received | | | 12/13/2013 | | DONE |
Christina Prado
|
|
|
Received three sets of revised plan sheets marked MG1.3; Gave to Sam for further review
|
GCB-Fndatn/slab ins/fld vent | 12/6/2013 | 12/6/2013 | 12/6/2013 | P | PEND |
Tony Young
|
|
|
Herb ###-#### Pouring cement 12/9 at 9:00,, pending special inspection and cold weather provisions
|
Plan assigned to (SRZ) | 11/21/2013 | 11/21/2013 | 12/6/2013 | | DONE |
Sam Zahorka
|
|
|
Pending Mechanical to PASS plan modifications.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2013 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/6/2013 | | DONE |
Barbara Stitt
|
|
|
Issue plan modification
|
Routing - PLAN CHECK | 12/4/2013 | | 12/6/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 12/6/2013 | | 12/6/2013 | | PASS |
Troy James
|
|
|
plan mod
|
Routing - PLAN CHECK | 12/4/2013 | | 12/4/2013 | | PEND |
Sam Zahorka
|
|
|
Pending Mechanical to PASS.
|
Routing Off Site - STRUCTURAL | 11/27/2013 | | 12/4/2013 | | PASS |
Sam Zahorka
|
|
|
Plan Modification after permit issuance.--Called Action Courier for pick up on 11-27-13 @ 2:55pm//BAS
|
GCB-Footing | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Tom Arcoraci
|
|
|
Herb ###-#### He would like closest to noon as possible, call first please spec inspec on site
|
Routing - PLAN CHECK | 11/25/2013 | | 11/27/2013 | | PEND |
Sam Zahorka
|
|
|
Pending Structural to PASS
|
Routing - Mechanical Review | 11/21/2013 | | 11/25/2013 | | FAIL |
Troy James
|
|
|
need to revise the comcheck to reflect the new air conditioner
|
Routing - Plumbing Review | 11/25/2013 | | 11/25/2013 | | PASS |
Bill VanDegrift
|
|
|
plan mod ok
|
GCB-Footing | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Tom Arcoraci
|
|
|
Herb ###-####
|
Plan resubmittals received | | | 11/21/2013 | | |
|
|
|
Plan modification-Received 4 copies of sheets A0.1, A0.2, C2.0, L1.1, L1.2, A1.0, A2.0, A2.1, A2.2, A2.3, A2.4, A2.5, A2.6, A2.7, A2.8, A2.9, A3.0, A3.1, A5.0, A5.1, A5.2, A5.3, A5.4, A5.5, A5.6, A5.7, A6.3, A6.4, A9.0, A9.1, A9.3, S2.0, S2.1, S2.2, S2.3, S2.4, S2.5, S2.6, S2.7, S2.8, S2.9, M1.4, M4.0, P1.1, P1.4, P2.1, P2.2, P2.4, P3.0, P5.0, E1.0, E2.0, E3.0, E5.0, E6.0, E7.0, E9.0, E10.0, E12.0, E14.0 and started routing with mechanical
|
GCB-Fndatn/slab ins/fld vent | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | PART |
Mike Jordan
|
|
|
Herb ###-#### Geotech inspecting rebar also for noon foundation pour. Work in progress, pending special inspection, stemwall exterior of building, south side.
|
GCB-Fndatn/slab ins/fld vent | 11/14/2013 | 11/15/2013 | 11/15/2013 | A | PASS |
Mike Jordan
|
|
|
Herb ###-#### Rebar for foundation inspection. East stemwall ok.
|
GCB-Footing | 11/12/2013 | 11/12/2013 | 11/13/2013 | A | PASS |
Tom Arcoraci
|
|
|
Herb ###-#### (2:00 concrete pour) spec insp on site
|
GCB-Footing | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PART |
Tony Young
|
|
|
Herb ###-####,, work in progress,, special inspector on site,, back (south footing)
|
GCB-Courtesy | 11/5/2013 | 11/6/2013 | 11/6/2013 | A | DONE |
Mike Jordan
|
|
|
Herb ###-#### Call prior. Went over concrete special inspection requirements with contractor.
|
Telephone call | | | 10/29/2013 | | DONE |
Sam Zahorka
|
|
|
Left message for the architect.
|
Plan resubmittals received | | | 10/11/2013 | | |
|
|
|
Received 1 copy of sheets C1.0, C1.1, C2.0, C3.0, C3.1, C3.2, C4.0, C4.1, C4.2, C5.0, C5.1, C5.2, C5.3, C5.4, C6.0, C6.1, C7.0, C7.1, C7.2, C8.0, L1.0, L1.1, L1.2 and taken to Sam Zahorka's desk
|
Issue and Courier | | | 10/9/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 7/29/2013 | 7/29/2013 | 10/1/2013 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - PLAN CHECK | 10/1/2013 | | 10/1/2013 | | PASS |
Sam Zahorka
|
|
|
Sent two approved copires to Garden City. Garden City will make a third copy and deliver back to me per Lori.
|
Routing - Plumbing Review | 10/1/2013 | | 10/1/2013 | | PASS |
Bill VanDegrift
|
|
|
corrections made
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2013 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 9/30/2013 | | |
|
|
|
Received 3 copies of sheets P1.1, P1.2, P4.0, P4.1 and taken to Sam Zahorka's desk
|
Routing - Plumbing Review | 9/25/2013 | | 9/26/2013 | | FAIL |
Bill VanDegrift
|
|
|
1) Provide fixture count showing water closets to Garden City Public Works.
2) UPC table 7-3 note 5-- provide 4" waste to 1st. clothes washer
3) Idaho State Plumbing code--2" min. waste below grade.riser diagrams.
4) ISPC--cleanouts on 2" waste at 50' intervals..
5) UPC 807.2 air conditioning condensate from public area may not be connected to private room sink tail piece.
|
Routing - Mechanical Review | 9/18/2013 | | 9/25/2013 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 9/24/2013 | | |
|
|
|
Received 4 copies of sheets M1.1, M1.2, M2.2, M4.1 and taken to add to plans in MEC review
|
Plan resubmittals received | | | 9/20/2013 | | |
|
|
|
Received 1 copy of review comments and response log, 3 copies of sheets A1.0, A1.1, C2.0, C3.1
|
Routing - PLAN CHECK | 9/18/2013 | | 9/18/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing Off Site - STRUCTURAL | 9/13/2013 | | 9/17/2013 | | PASS |
Sam Zahorka
|
|
|
Called Action Courier for pick up on 9-13-13 @ 11:35am//BAS
|
Plan resubmittals received | | | 9/11/2013 | | |
|
|
|
Received 4 copies of Fire Resistance Ratings-ANSI/UL 263, 4 copies of plan review response, 4 copies of Statment of Special Inspections, 4 copies of Supplemental Strucural Calcs, 4 copies of sheets A0.0, A0.1, A2.1, A2.2, A2.3, A2.4, A3.0, A3.2, A4.0, A6.0, A6.1, A7.5, A7.6, A9.0, A9.1, A9.2, A10.0, E1.0, E2.0, E6.0, E14.0, M1.1, M2.1, P1.1, P1.2, P1.3, P1.4, P2.1, P2.2, P2.3, P2.4, P4.0, P4.1, P6.0, S2.1, S2.2, S2.3, S2.4, S2.6, S4.0 and taken to Sam Zahorka's desk
|
Routing Off Site - STRUCTURAL | 8/15/2013 | | 8/30/2013 | | FAIL |
Sam Zahorka
|
|
|
Called Action Couier for pick up
|
1st review completed | | | 8/23/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | | | 8/23/2013 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 7/29/2013 | | 8/5/2013 | | FAIL |
Troy James
|
|
|
1) I believe the entire ceiling is 1-hour rated assembly. You have noted that all penetrations shall be protected with fire dampers. I believe the corridor needs to be protected with fire/smoke dampres. Please show or note on plans the required locations for fire/smoke dampers
2) verify the grease exhaust termination is above the highest point of sloped roof. If not, we will need to terminate 10' away.
3) show how you are complying with IMC 507.2.1.1.
|
Application received | | | 11/20/2012 | | DONE |
|
|
|
|