Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberGCB12-00156
StatusFinaled
Name K2 CONSTRUCTION
Site Address 9995 W STATE ST
Project NameBLD2012-00156
Customer Number 
ePlanReviewNo
Description
Grace At State Street - **71/11/14 PLAN MODIFICATION TO INCLUDE: MECHANICAL CHANGES AS APPROVED BY MECHANICAL PLAN REVIEW. SRZ***11/26/13 PLAN MODIFICATIONS TO INCLUDE: REMOVED PATIOS AND EXTERIOR UNIT DOORS ON NORTH AND EAST SIDES; REMOVED NORTH-MOST CARPORT AT THE EAST SIDE LOCATION; REDUCED THE SIZE OF THE UNIT ENTRY DOORS DUE TO NO BED MOVEMENT AND LIMITED CARE LICENSING; REMOVED 2-HOUR FIRE WALL EXTENSIONS; MIRRORED UNIT 266; PLUMBING, MECHANICAL, ELECTRICAL MODIFICATIONS PER PLANS; AND ALLOTHER MODIFICATIONS PER ADDENDUM NO.2. SRZ*** Scope of work includes construction of a 70,679 sq. ft., single story, fully sprinklered, Type VA construction, divided by (6) 2-hour fire walls to create four buildings for allowable floor area compliance based on type of construction (13, 122 sq. ft. / 35,634 sq. ft. / 12,797 sq. ft. / 9,126 sq. ft.); with 85 supervised residential units (38 one bedroom units @ 576 sq. ft.; 40 Studio Units @ 416 sq. ft.; 1 Studio Unit @ 523; 4 two bedroom units @ 818 sq. ft.; and 2 two bedroom units @ 780 sq. ft.; use of 2-hour fire walls and (3) 1-hour smoke barrier walls create (6) smoke compartments; 1-hour smoke partitions to create a smoke resistant corridor system; a kitchen, dining and socializing area; laundry, mechanical and common use support areas. There are four interior courts (3,966 sq. ft. / 3,044 sq. ft. / 5,734 sq. ft. / 4,015 sq. ft.) that exit back through the facility; installation of electrical, mechanical, plumbing, sprinkler and alarm systems; and all associated site work and landscaping. All work per the approved plans, attached plan review comments, and conditions of all reviewing agencies for this project. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final9/18/20149/18/20149/18/2014PPASS
DetailsJim Sly
Julio ###-####
GCB-Final9/16/20149/17/20149/17/2014PPART
DetailsJim Sly
Julio ###-####
OK for Temp Occ. OK for Perm Occ when all other agencies are approved for Perm Occ.
GCB-Final9/16/20149/16/20149/16/2014PPEND
DetailsJim Sly
Julio ###-####
Walk thru
GCB-Framing9/15/20149/15/20149/15/2014PPASS
DetailsDave Hannah
Julio ###-#### canopy framing inspectino request
GCB-Ceiling Grid9/4/20149/5/20149/5/2014APART
DetailsJim Sly
Julio ###-####
Select ceiling grid OK.
GCB-Framing8/14/20148/15/20148/15/2014APART
DetailsJim Sly
###-#### Julio
Verified installation of Tenmat FF109X fire rated light covers above can lights. Product approved by Sam Zahorka plan check.
GCB-Framing7/31/20148/1/20148/1/2014ACANC
DetailsJim Sly
GCB-Framing7/21/20147/22/20147/22/2014APASS
DetailsJim Sly
Julio ###-####
GCB-Framing7/10/20147/11/20147/11/2014APASS
DetailsJim Sly
Julio ###-####
Completes all framing insp.
Plan assigned to (SRZ)7/10/20147/10/20147/11/2014 DONE
DetailsSam Zahorka
Grace Plan Mod for Mechanical
PLANS/APPL TAKEN TO FRONT DESK  7/11/2014 DONE
DetailsSam Zahorka
Routing - PLAN CHECK7/10/2014 7/11/2014 PASS
DetailsSam Zahorka
Plan modification processing
CHANGE STATUS TO (ISS)  7/11/2014 DONE
DetailsSam Zahorka
Telephone call  7/10/2014 DONE
DetailsSam Zahorka
provided clarification to duct/air transfer penetration openings over the telephone to a gentleman named Robin which is the mechanical contractor for this job. I explained when the roof/ceiling assembly transitions from 9 feet to 12 feet you’ll need to add dampers wherever the ducts penetrate the 1-hour ceiling, whether it’s a horizontal membrane or a vertical membrane. If the assembly transitions vertical, add sheetrock to the attic truss matching the rating (sheetrock layers) of the 1-hour roof ceiling assembly and still add a damper.
CHANGE STATUS TO (REV)  7/10/2014  
DetailsSam Zahorka
Plan modifications for Mechanical Received.
Routing - Mechanical Review7/10/2014 7/10/2014 PASS
DetailsTroy James
Plan modifications for mechanical sheets
Plan resubmittals received  7/9/2014  
Received 2 copies of sheets M1.2, M2.2, M4.1 and taken to Sam Zahorka
GCB-Framing7/7/20147/8/20147/8/2014APART
DetailsJim Sly
Julio ###-####
Conf.
GCB-Framing6/30/20147/1/20147/1/2014APART
DetailsMike Jordan
Julio ###-####. Framing at northwest qudrant and front canopy. Needs to install roll blocking on trusses at interior bearing wall locations. also discussed plan for can lights in rated roof/ceiling assemblies.
GCB-Framing6/20/20146/23/20146/23/2014APASS
DetailsJim Sly
Julio ###-####
Rooms only......2hr wall to West exterior wall.
GCB-Framing6/17/20146/20/20146/20/2014ACANC
DetailsMike Jordan
Julio ###-####. Inspection cancelled.
GCB-Framing6/16/20146/16/20146/16/2014PCANC
DetailsMike Jordan
Julio ###-####. Per phone call from julio, inscpection was cancelled.
GCB-Framing6/10/20146/12/20146/12/2014APART
DetailsJim Sly
Julio ###-####
Framing insp ....far West wing OK C/N No openings within 4' 2hr wall, Non rated can lights in rated ceiling. Method to close 1/2" gap at top of walls with hat channel, provide fire/smoke dampers at make up air...Hood.
GCB-Framing6/6/20146/9/20146/9/2014PPART
DetailsJim Sly
Julio ###-####
Select Areas.
GCB-Energy6/4/20146/6/20146/6/2014APART
DetailsJim Sly
Julio ###-#### spoke with Jim Sly about this inspection
Sect 1.....OK
GCB-Fire Wall6/4/20146/6/20146/6/2014APASS
DetailsJim Sly
Julio ###-#### spoke with Jim Sly about this inspection
#2 2hr wall OK.
GCB-Framing6/4/20146/6/20146/6/2014APART
DetailsJim Sly
Julio
Area 2.......OK
GCB-Energy6/4/20146/4/20146/4/2014APART
DetailsJim Sly
Julio ###-####
2hr wall to East end of bldg.
GCB-Assembly6/2/20146/4/20146/4/2014APART
DetailsJim Sly
Julio ###-#### roof sheeting inspection requested
Select roof nailing.
GCB-Fire Wall6/2/20146/2/20146/2/2014PPASS
DetailsJim Sly
Julio ###-####
Rooms only .........Framing and Firestopping OK far East wing......up to 2 hr wall
GCB-Fire Wall5/30/20146/2/20146/2/2014ANR
DetailsJim Sly
Julio ###-#### for a firestop
GCB-Assembly5/29/20146/2/20146/2/2014APASS
DetailsJim Sly
Julio ###-#### roof and wall sheeting (?) inspection requested
N and W walls OK Roof OK
GCB-Fire Wall5/29/20145/30/20145/30/2014ADONE
DetailsJim Sly
Julio ###-####
Conference on Firestopping.
GCB-Assembly5/28/20145/29/20145/29/2014APART
DetailsMike Jordan
FIRE STOPS OTHER JULIO ###-####. SWork in progress on firestopping at area 1. Double layer 5/8 type x being installed in concelled areas behind tub and pex is being firecaulked. Electrical not yet started. K2 to call for additional inspection whwn area 1 is completed.
GCB-Framing5/23/20145/27/20145/27/2014APART
DetailsJim Sly
Julio
Framing OK 2 East wings..... Need firestopping and listings. Do not insulate.
GCB-Assembly5/21/20145/23/20145/23/2014APART
DetailsTony Young
Julio ###-#### roof sheet/structural inspection request
roof nailing ok
GCB-Shearwall5/6/20145/7/20145/7/2014APASS
DetailsMike Jordan
Julio ###-####. Exterior shear walls, north east portion and courtyards 1 and 2.
GCB-Framing5/1/20145/2/20145/2/2014APART
DetailsTom Arcoraci
Julio ###-#### roof framing/roof sheathing inspection requeste wip ok
GCB-Assembly4/24/20144/25/20144/25/2014APART
DetailsJim Sly
Julio ###-#### roof nailing inspection request
Section N. of Courtyard #3.....OK Circled on plan sheet.
GCB-Assembly4/21/20144/22/20144/22/2014PNR
DetailsJim Sly
Herb ###-#### roof nailing inspection request; partial
No access.
GCB-Assembly4/15/20144/16/20144/17/2014APART
DetailsDave Hannah
Herb ###-#### roof nailing inspection ok to cover see area marked on plans
GCB-Assembly4/14/20144/14/20144/14/2014PNR
DetailsJim Sly
Roof nailing.
GCB-Assembly4/11/20144/14/20144/14/2014ACANC
DetailsJim Sly
Herb ###-#### roof nailing inspection
GCB-Assembly4/7/20144/8/20144/8/2014APART
DetailsTony Young
Herb ###-#### roof nailing inspection request Grace Assitsted Living,, far east wing ok
Plan assigned to (SRZ)1/6/20141/6/20141/8/2014 DONE
DetailsSam Zahorka
Carport has own BLD. See BLD2###-####2
CHANGE STATUS TO (ISS)  1/8/2014 DONE
DetailsSam Zahorka
GCB-Fndatn/slab ins/fld vent12/27/201312/30/201312/30/2013APASS
DetailsDave Hannah
Herb ###-#### Pour at 10:30 am
Plan resubmittals received  12/27/2013  
Received 4 copies of structural calcs for single-post carport, 4 copies of site plan, 4 copies of design calcs from Tim Covert P.E. Structural Engineer for Steelport Single-post Carport and taken to Sam's desk
GCB-Footing12/23/201312/24/201312/26/2013APART
DetailsDave Hannah
Herb ###-#### pouring at 9:30 am forms up and horz rebar in ground was coverd so there is no frost ok to place concrete
Routing - PLAN CHECK12/26/2013 12/26/2013 PASS
DetailsSam Zahorka
Verified Garden City Plan Mod set was identical to plan mod set approved on 11/26/13. Provided approved stamp and signature. Routed back to Garden City.
GCB-Footing12/20/201312/20/201312/20/2013PDEFR
DetailsMike Jordan
Herb ###-#### (1:30 pour). Pending special inspection.
GCB-Fndatn/slab ins/fld vent12/17/201312/18/201312/18/2013PPART
DetailsMike Jordan
Herb ###-#### Foundation pour at 1:30. Spoke therb. concrete has been placed. special inspector on site.
GCB-Fndatn/slab ins/fld vent12/16/201312/17/201312/18/2013PPART
DetailsJim Sly
Herb ###-#### pour at 1:30 special inspection provided
Select walls at NE and SE sect. OK pend. Geotech special inspections, tests and approvals.
GCB-Fndatn/slab ins/fld vent12/12/201312/13/201312/13/2013APART
DetailsTom Arcoraci
Herb ###-#### pouring concrete at noon spec inspector on site
Plan assigned to (SRZ)12/13/201312/13/201312/13/2013 DONE
DetailsSam Zahorka
Routing - PLAN CHECK12/13/2013 12/13/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  12/13/2013 DONE
CHANGE STATUS TO (ISS)  12/13/2013 DONE
DetailsBarbara Stitt
Issue plan modification
Plan resubmittals received  12/13/2013 DONE
DetailsChristina Prado
Received three sets of revised plan sheets marked MG1.3; Gave to Sam for further review
GCB-Fndatn/slab ins/fld vent12/6/201312/6/201312/6/2013PPEND
DetailsTony Young
Herb ###-#### Pouring cement 12/9 at 9:00,, pending special inspection and cold weather provisions
Plan assigned to (SRZ)11/21/201311/21/201312/6/2013 DONE
DetailsSam Zahorka
Pending Mechanical to PASS plan modifications.
PLANS/APPL TAKEN TO FRONT DESK  12/6/2013 DONE
DetailsSam Zahorka
CHANGE STATUS TO (ISS)  12/6/2013 DONE
DetailsBarbara Stitt
Issue plan modification
Routing - PLAN CHECK12/4/2013 12/6/2013 PASS
DetailsSam Zahorka
Routing - Mechanical Review12/6/2013 12/6/2013 PASS
DetailsTroy James
plan mod
Routing - PLAN CHECK12/4/2013 12/4/2013 PEND
DetailsSam Zahorka
Pending Mechanical to PASS.
Routing Off Site - STRUCTURAL11/27/2013 12/4/2013 PASS
DetailsSam Zahorka
Plan Modification after permit issuance.--Called Action Courier for pick up on 11-27-13 @ 2:55pm//BAS
GCB-Footing12/2/201312/2/201312/2/2013PPASS
DetailsTom Arcoraci
Herb ###-#### He would like closest to noon as possible, call first please spec inspec on site
Routing - PLAN CHECK11/25/2013 11/27/2013 PEND
DetailsSam Zahorka
Pending Structural to PASS
Routing - Mechanical Review11/21/2013 11/25/2013 FAIL
DetailsTroy James
need to revise the comcheck to reflect the new air conditioner
Routing - Plumbing Review11/25/2013 11/25/2013 PASS
DetailsBill VanDegrift
plan mod ok
GCB-Footing11/21/201311/22/201311/22/2013PPASS
DetailsTom Arcoraci
Herb ###-####
Plan resubmittals received  11/21/2013  
Plan modification-Received 4 copies of sheets A0.1, A0.2, C2.0, L1.1, L1.2, A1.0, A2.0, A2.1, A2.2, A2.3, A2.4, A2.5, A2.6, A2.7, A2.8, A2.9, A3.0, A3.1, A5.0, A5.1, A5.2, A5.3, A5.4, A5.5, A5.6, A5.7, A6.3, A6.4, A9.0, A9.1, A9.3, S2.0, S2.1, S2.2, S2.3, S2.4, S2.5, S2.6, S2.7, S2.8, S2.9, M1.4, M4.0, P1.1, P1.4, P2.1, P2.2, P2.4, P3.0, P5.0, E1.0, E2.0, E3.0, E5.0, E6.0, E7.0, E9.0, E10.0, E12.0, E14.0 and started routing with mechanical
GCB-Fndatn/slab ins/fld vent11/19/201311/20/201311/20/2013APART
DetailsMike Jordan
Herb ###-#### Geotech inspecting rebar also for noon foundation pour. Work in progress, pending special inspection, stemwall exterior of building, south side.
GCB-Fndatn/slab ins/fld vent11/14/201311/15/201311/15/2013APASS
DetailsMike Jordan
Herb ###-#### Rebar for foundation inspection. East stemwall ok.
GCB-Footing11/12/201311/12/201311/13/2013APASS
DetailsTom Arcoraci
Herb ###-#### (2:00 concrete pour) spec insp on site
GCB-Footing11/7/201311/8/201311/8/2013APART
DetailsTony Young
Herb ###-####,, work in progress,, special inspector on site,, back (south footing)
GCB-Courtesy11/5/201311/6/201311/6/2013ADONE
DetailsMike Jordan
Herb ###-#### Call prior. Went over concrete special inspection requirements with contractor.
Telephone call  10/29/2013 DONE
DetailsSam Zahorka
Left message for the architect.
Plan resubmittals received  10/11/2013  
Received 1 copy of sheets C1.0, C1.1, C2.0, C3.0, C3.1, C3.2, C4.0, C4.1, C4.2, C5.0, C5.1, C5.2, C5.3, C5.4, C6.0, C6.1, C7.0, C7.1, C7.2, C8.0, L1.0, L1.1, L1.2 and taken to Sam Zahorka's desk
Issue and Courier  10/9/2013 DONE
DetailsBarbara Stitt
Plan assigned to (SRZ)7/29/20137/29/201310/1/2013 DONE
DetailsSam Zahorka
1st review completed.
Routing - PLAN CHECK10/1/2013 10/1/2013 PASS
DetailsSam Zahorka
Sent two approved copires to Garden City. Garden City will make a third copy and deliver back to me per Lori.
Routing - Plumbing Review10/1/2013 10/1/2013 PASS
DetailsBill VanDegrift
corrections made
PLANS/APPL TAKEN TO FRONT DESK  10/1/2013 DONE
DetailsSam Zahorka
Plan resubmittals received  9/30/2013  
Received 3 copies of sheets P1.1, P1.2, P4.0, P4.1 and taken to Sam Zahorka's desk
Routing - Plumbing Review9/25/2013 9/26/2013 FAIL
DetailsBill VanDegrift
1) Provide fixture count showing water closets to Garden City Public Works.
2) UPC table 7-3 note 5-- provide 4" waste to 1st. clothes washer
3) Idaho State Plumbing code--2" min. waste below grade.riser diagrams.
4) ISPC--cleanouts on 2" waste at 50' intervals..
5) UPC 807.2 air conditioning condensate from public area may not be connected to private room sink tail piece.
Routing - Mechanical Review9/18/2013 9/25/2013 PASS
DetailsTroy James
Plan resubmittals received  9/24/2013  
Received 4 copies of sheets M1.1, M1.2, M2.2, M4.1 and taken to add to plans in MEC review
Plan resubmittals received  9/20/2013  
Received 1 copy of review comments and response log, 3 copies of sheets A1.0, A1.1, C2.0, C3.1
Routing - PLAN CHECK9/18/2013 9/18/2013 PASS
DetailsSam Zahorka
Routing Off Site - STRUCTURAL9/13/2013 9/17/2013 PASS
DetailsSam Zahorka
Called Action Courier for pick up on 9-13-13 @ 11:35am//BAS
Plan resubmittals received  9/11/2013  
Received 4 copies of Fire Resistance Ratings-ANSI/UL 263, 4 copies of plan review response, 4 copies of Statment of Special Inspections, 4 copies of Supplemental Strucural Calcs, 4 copies of sheets A0.0, A0.1, A2.1, A2.2, A2.3, A2.4, A3.0, A3.2, A4.0, A6.0, A6.1, A7.5, A7.6, A9.0, A9.1, A9.2, A10.0, E1.0, E2.0, E6.0, E14.0, M1.1, M2.1, P1.1, P1.2, P1.3, P1.4, P2.1, P2.2, P2.3, P2.4, P4.0, P4.1, P6.0, S2.1, S2.2, S2.3, S2.4, S2.6, S4.0 and taken to Sam Zahorka's desk
Routing Off Site - STRUCTURAL8/15/2013 8/30/2013 FAIL
DetailsSam Zahorka
Called Action Couier for pick up
1st review completed  8/23/2013 DONE
DetailsSam Zahorka
Routing - PLAN CHECK  8/23/2013 FAIL
DetailsSam Zahorka
Sam Zahorka
Routing - Mechanical Review7/29/2013 8/5/2013 FAIL
DetailsTroy James
1) I believe the entire ceiling is 1-hour rated assembly. You have noted that all penetrations shall be protected with fire dampers. I believe the corridor needs to be protected with fire/smoke dampres. Please show or note on plans the required locations for fire/smoke dampers
2) verify the grease exhaust termination is above the highest point of sloped roof. If not, we will need to terminate 10' away.
3) show how you are complying with IMC 507.2.1.1.
Application received  11/20/2012 DONE