GCB-Final | 2/14/2014 | 2/18/2014 | 2/18/2014 | A | PASS |
Jim Sly
|
|
|
Larry Mahr ###-#### Structural Final ......OK.
|
GCB-Final | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | NR |
Jim Sly
|
|
|
Larry Mahr ###-#### Called Lori at Garden City to verify that Fire has finaled. Need fire final inspection.
|
GCB-Framing | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PASS |
Tony Young
|
|
|
###-####
|
GCB-Framing | 3/13/2013 | 3/14/2013 | 3/14/2013 | P | PASS |
Mike Jordan
|
|
|
Steve @ ###-#### or ###-#### PM Inspection Call in advance. Interior wood framed walls for new reception area and counseling rooms.
|
Plan assigned to (SRZ) | 11/27/2012 | 11/27/2012 | 1/11/2013 | | DONE |
Sam Zahorka
|
|
|
1st review completed. Corrections needed.
|
Routing - PLAN CHECK | 1/11/2013 | | 1/11/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2013 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 1/11/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 1/9/2013 | | |
|
|
|
Received 3copies of plan review response letter dated 1-8-13 from Wayne Thoeless to Sam Zahorka with attachments, 3 copies of sheets Cover, C1.1, A1.1, A1.2, E1.2 and taken to Sam Zahorka's desk
|
Routing - PLAN CHECK | 11/27/2012 | | 12/11/2012 | | FAIL |
Sam Zahorka
|
|
|
|
1st review completed | | | 12/11/2012 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 11/21/2012 | | DONE |
|
|
|
|