Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberGCB12-00162
StatusIssued
Name Bricon, Inc.
Site Address 201 E 46TH Unit: PARKS & PW STG
Project NameBLD2012-00162
Customer Number 
ePlanReviewNo
Description
46th St Booster Pump Station - To construct a new 1,047 square foot booster pump station building and associated site work. The booster pump station building construction will include: a concrete slab foundation, CMU wall construction, pre-engineered/manufactured roof trusses, and asphalt roofing. All work per the approved plans and all other reviewing agencies approvals. SPECIAL INSPECTIONS and STRUCTURAL OBSERVATIONS ARE REQUIRED. This building is NOT fire sprinklered. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final9/6/20139/6/20139/6/2013PNR
DetailsJim Sly
Mark ###-#### Call 20 min prior
Need approved plan, final letter of approval from STRATA and Fire final.
GCB-Framing4/29/20134/30/20134/30/2013PPASS
DetailsTom Arcoraci
Mark @ ###-####
PM Inspection
GCB-Stem wall3/13/20133/14/20133/14/2013PPART
DetailsMike Jordan
Mark @ ###-####
PM Inspection. Perimeter stemwall ok. Also reviewed rfi from engineer of record deleting the transverse reinforcement in footing. Also reviewed special inspection report.
GCB-Footing3/11/20133/12/20133/12/2013APART
DetailsMike Jordan
Mark ###-#### requested by 10AM if possible. Perimeter footing for pump station. Will have special inspection. (strata) Contractor to provide RFI from engineer of record deleting the #5 transverese reinforcement at 16 inches o.c. in the footing as shown on approved plans.
Plan assigned to (SRZ)12/12/201212/12/20121/9/2013 DONE
DetailsSam Zahorka
1st review completed. Additional information needed.
Routing - PLAN CHECK1/9/2013 1/9/2013 PASS
DetailsSam Zahorka
Booster Pump Station building only. Reservoir and its foundation require separate permits.
Telephone call  1/9/2013 DONE
DetailsSam Zahorka
Telephone call with the applicant requesting to remove the Resevoir and its foundation from this permit. THis permit only includes the Booster pump station building. Separate permits are required for the Reservoir and it's foundation.
PLANS/APPL TAKEN TO FRONT DESK  1/9/2013 DONE
DetailsSam Zahorka
Issue and Courier  1/9/2013 DONE
DetailsBarbara Stitt
Routing - Mechanical Review12/24/2012 12/26/2012 PASS
DetailsTroy James
Routing - Plumbing Review12/26/2012 12/26/2012 PASS
DetailsBill VanDegrift
Per plans and 2003 UPC.
Routing - PLAN CHECK12/12/2012 12/24/2012 FAIL
DetailsSam Zahorka
Additional information requested from the Engineer for the reservoir foundation. This information is needed prior to permit issuance.
1st review completed  12/24/2012 DONE
DetailsSam Zahorka
Application received  12/11/2012 DONE