GCB-Final | 7/21/2014 | 7/22/2014 | 7/22/2014 | P | PASS |
Tony Young
|
|
|
ok for c of o
|
GCB-Final | 7/21/2014 | 7/22/2014 | 7/22/2014 | A | PEND |
Tony Young
|
|
|
|
GCB-Final | 7/16/2014 | 7/18/2014 | 7/18/2014 | A | FAIL |
Mike Jordan
|
|
|
Mark ###-####. Needs to provide the correct door hardware for required exits.
|
GCB-Energy | 4/22/2014 | 4/23/2014 | 4/23/2014 | A | PASS |
Jim Sly
|
|
|
Mark ###-#### re-inspect insulation
|
GCB-Framing | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | PASS |
Jim Sly
|
|
|
Corrections completed. OK to cover.
|
GCB-Energy | 4/14/2014 | 4/15/2014 | 4/15/2014 | P | PART |
Jim Sly
|
|
|
Mark ###-#### Note, this was originally scheduled for morning, request changed to afternoon C/N Roof insulation cannot have exposed Kraft Face. Insulation adjacent to attic space to be encapsulated on all 6 sides. Verify that a 60 # test was done on Gas Line. I Ok'd to rock up to 8' on all walls..........After gas test verified.
|
GCB-Energy | 4/11/2014 | 4/15/2014 | 4/15/2014 | A | FAIL |
Jim Sly
|
|
|
Mark ###-#### insulation No approved plans on site....C/N posted.
|
GCB-Framing | 4/1/2014 | 4/2/2014 | 4/2/2014 | P | PASS |
Dave Hannah
|
|
|
Mark ###-#### framing re-inspection
|
Plan assigned to (SRZ) | 3/26/2014 | 3/26/2014 | 3/28/2014 | | DONE |
Sam Zahorka
|
|
|
Plan Modification
|
Routing - PLAN CHECK | 3/26/2014 | | 3/28/2014 | | PASS |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/28/2014 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (REV) | | | 3/26/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 3/26/2014 | | |
|
|
|
Plan modification-sheets A3.06, A5.1, A5.2, A6.2-3 sets
|
GCB-Framing | 3/19/2014 | 3/20/2014 | 3/24/2014 | P | PART |
Dave Hannah
|
|
|
Mark ###-#### fire blocking and seal package shear ok to cover ext trusses ok framing ok note one hr fire wall around cremation room is a ? on how to do.
|
GCB-Courtesy | 2/18/2014 | 2/18/2014 | 2/19/2014 | P | PASS |
Jim Sly
|
|
|
Mark ###-#### Rebar on trash enclosure
|
CHANGE STATUS TO (ISS) | | | 2/7/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 2/5/2014 | 2/5/2014 | 2/6/2014 | | DONE |
Sam Zahorka
|
|
|
Plan modification
|
Routing - PLAN CHECK | 2/5/2014 | | 2/6/2014 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Mechanical Review | 2/6/2014 | | 2/6/2014 | | PASS |
Troy James
|
|
|
Plan Mod
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2014 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (REV) | | | 2/5/2014 | | |
|
|
|
Revised plans submited 2-5-14
|
Plan resubmittals received | | | 2/5/2014 | | |
|
|
|
Received cover transmittal, 3 copies of sheets A3.6, A5.1, A5.2, A6.2 and taken to Sam Zahorka's desk
|
GCB-Footing | 11/7/2013 | 11/7/2013 | 11/7/2013 | P | PEND |
Tony Young
|
|
|
Mike ###-####,, special inspection report,, interior footings
|
GCB-Footing | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | PEND |
Tony Young
|
|
|
Mark ###-####,, ok pending special inspection
|
GCB-Stem wall | 10/28/2013 | 10/29/2013 | 10/29/2013 | P | PASS |
Dave Hannah
|
|
|
Mark ###-####
|
GCB-Footing | 10/22/2013 | 10/23/2013 | 10/23/2013 | A | PART |
Mike Jordan
|
|
|
Mark ###-####. Provide the additional #4 rebar mat at nw wing of bldg. Special inspector to verify.
|
Issue and Courier | | | 7/30/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 5/8/2013 | 5/8/2013 | 7/29/2013 | | DONE |
Sam Zahorka
|
|
|
1st Review completed. Corrections needed.
|
Plan resubmittals received | | | 7/29/2013 | | |
|
|
|
Received 3 copies of plan review response, 1 copy of cross access easement agreement, 1 copy of statment of special inspections, 1 copy of structural calculations, 1 copy of structural insulated panels, 3 copies of sheets 0.1, A0.1, A1.0, A2.1, A3.5, A3.4, A6.2, A7.1, A7.2, A8.1, L1.0, C1.0, C2.0, C3.0, C3.1, C4.0, C5.0, M2.1, M1.0, E1.0, E2.0 and taken to Sam Zahorka's desk
|
Routing - PLAN CHECK | 7/29/2013 | | 7/29/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/29/2013 | | DONE |
Sam Zahorka
|
|
|
|
Meeting | | | 7/22/2013 | | DONE |
Sam Zahorka
|
|
|
The architect visited the City of Boise PDS and wanted to provide his signatures on his stamped plans. I brought his plans to the front desk and he signed them.
|
Telephone call | | | 7/17/2013 | | DONE |
Sam Zahorka
|
|
|
Spoke with Cheryl Bowman about needed corrections and Special Inspection information in order to complete the plan review for this project. I requested her to set up a meeting at Garden City with her architect to communicate needed items to expedite permitting. She said she would schedule the meeting with Garden City.
|
Telephone call | | | 7/15/2013 | | DONE |
Sam Zahorka
|
|
|
Called the owner and discussed the building permit status. Emailed the 1st Building Plan Review report and dates of telephone and email correspondance between myself and the architect.
|
Telephone call | | | 6/10/2013 | | DONE |
Sam Zahorka
|
|
|
Called the architect and requested structural for the proposed human creamation furnace. The information for the furnace was not provided prior to the 1st review being completed. engineering and calculations are needed to verify the proposed slab thickness is adequate to carry the furnaces weight of 18,126 lbs. Also sent an email requesting addtional engineering.
|
1st review completed | | | 5/24/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/14/2013 | | 5/24/2013 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - Plumbing Review | 5/13/2013 | | 5/14/2013 | | PASS |
Daryl Spivey
|
|
|
Per plan and 2009 ISPC.
|
Routing - Mechanical Review | 5/8/2013 | | 5/13/2013 | | PASS |
Troy James
|
|
|
|
CHANGE STATUS TO (REV) | | | 4/16/2013 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | | 4/1/2013 | | DONE |
|
|
|
|