Permit Information
Permit NumberGCB13-00064
StatusFinaled
Name Good Cacao
Site Address 5307 N GLENWOOD
Project NameBLD2013-00063
Customer Number 
ePlanReviewNo
Description
Good Cacao TI - To remodel a 775 square foot interior portion of an existing building for this tenant. Work to include: construct new interior walls to create two new fully accessible mens and womens restrooms and locker rooms with benches, and a new break room; construct an engineered structural roof ceiling system over the new break room and restrooms for a future office area above; extend an existing stair enclosure wall to the bottom of the existing roof trusses; construct a new wall from the 2nd floor HVAC platform to the bottom the existing roof trusses; install a service sink; related interior finishes in compliance with chapter 8 of the 2009 IBC; plumbing, electrical work; install new emergency light fixtures and illuminated exit signs; and all other work per the approved plans, attached plan review report, and all other reviewing agencies approvals. A new Certificate of Occupancy with the new occupant load total is to be issued when completed and approved. Separate electrical and plumbing permits are required. **NOTE: This building is fully fire sprinklered for area increase. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department and will require a separate permit. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final8/23/20138/28/20138/28/2013APASS
DetailsMike Jordan
Drew ###-####. Structural final only ok.
GCB-Framing7/11/20137/11/20137/11/2013PPASS
DetailsJim Sly
Garrett ###-#### please call first
GCB-Framing7/9/20137/10/20137/11/2013PPART
DetailsJim Sly
Garrett ###-#### late afternoon if possible, please call first
Foam seal at plates....OK.
GCB-Framing7/9/20137/9/20137/9/2013PFAIL
DetailsMike Jordan
Garrett ###-####. Remove insulation for framing inspection. Foam seal all penetration s in top plates. Lag ledger as per engineering.
Issue and Courier  6/3/2013 DONE
DetailsBarbara Stitt
Plan assigned to (SRZ)5/3/20135/3/20135/31/2013 DONE
DetailsSam Zahorka
1st review completed.
Routing - PLAN CHECK5/31/2013 5/31/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  5/31/2013 DONE
DetailsSam Zahorka
Telephone call  5/31/2013 DONE
DetailsSam Zahorka
Called the Engineer Scott Soule. He does not allow any modification to the proposed size of the future 2nd floor office area unless additional engineering is performed. I red-lined the plans to reflect no changes in the size of the original size of the future office area until an additonal engineered analysis is provided to the building department for review and approval. I alled Garret with this company and explained. The engineer stated he would verify no increase in proposed office would occur.
Plan resubmittals received  5/30/2013  
Received 3 copies of sheets G-001, A-101, A-201, E-101and taken to Sam Zahorka's desk
Routing - PLAN CHECK5/3/2013 5/17/2013 FAIL
DetailsSam Zahorka
Sam Zahorka
1st review completed  5/17/2013 DONE
DetailsSam Zahorka
Telephone call  5/17/2013 DONE
DetailsSam Zahorka
Called the architect Matt Huffield and discussed Plan Review comments. Explained needed correction items.
Plan resubmittals received  5/9/2013  
Received 3 copies of sheet E-102 and taken to Sam Zahorka's desk
Application received  5/1/2013 DONE