Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberGCB13-00070
StatusFinaled
Name Arete Investments Group
Site Address 3682 N ADAM ST
Project NameBLD2013-00069
Customer Number 
ePlanReviewNo
Description
Unit A - To construct a new 1,787 square foot (943 square foot 1st story / 844 square foot 2nd story), two story, three bedroom, two and a half bathroom, single family dwelling townhouse with a 466 square foot attached two car garage, and a 148 square foot covered front porch. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final1/15/20141/16/20141/16/2014PPASS
DetailsMike Jordan
Jeremy ###-####. Structural final ok.
GCB-Energy10/10/201310/10/201310/10/2013PPASS
DetailsMike Jordan
Jeremy ###-####
GCB-Framing10/8/201310/8/201310/8/2013PPASS
DetailsJim Sly
Jerremy ###-#### Need inspection as soon as possible
GCB-Framing10/2/201310/3/201310/3/2013APART
DetailsTom Arcoraci
Jeremy ###-#### Verify setbacks for fireplace vents wall at 3 ft
GCB-Framing9/26/20139/27/20139/27/2013PPART
DetailsJim Sly
Jeremy ###-####
Rated soffits OK.
GCB-Shearwall8/26/20138/27/20138/27/2013PPASS
DetailsDave Hannah
###-####
GCB-Fire Wall8/6/20138/7/20138/8/2013APART
DetailsDave Hannah
Jeremy ###-#### please call first the first floor section ok
GCB-Shearwall7/19/20137/19/20137/19/2013PPASS
DetailsTom Arcoraci
Mark-###-####
GCB-Stem wall7/19/20137/19/20137/19/2013PCANC
DetailsTom Arcoraci
GCB-Footing7/17/20137/18/20137/18/2013APASS
DetailsTom Arcoraci
Mark ###-#### Call first
Plan assigned to (SRZ)5/21/20135/21/20137/2/2013 DONE
DetailsSam Zahorka
Pending Mechanical tom PASS . 1st review completed.
Routing - Mechanical Review7/2/2013 7/2/2013 PASS
DetailsTroy James
PLANS/APPL TAKEN TO FRONT DESK  7/2/2013 DONE
DetailsSam Zahorka
Issue and Courier  7/2/2013 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK6/28/2013 6/28/2013 PASS
DetailsSam Zahorka
Plan resubmittals received  6/27/2013 DONE
DetailsChristina Prado
Received three sets of revised plans marked A1, A2, A3, A4, A5, A6, A7, A8 & A9; Plans taken to Sam Zahorka for review
1st review completed  5/29/2013 DONE
DetailsSam Zahorka
Routing - PLAN CHECK5/28/2013 5/29/2013 FAIL
DetailsSam Zahorka
Sam Zahorka
Routing - Mechanical Review5/28/2013 5/28/2013 FAIL
DetailsTroy James
emailed correction to teds heating
Routing - Mechanical Review5/21/2013 5/23/2013 FAIL
DetailsTroy James
left message to Teds Heating to call me
Application received  5/15/2013 DONE
Routing - PLAN CHECK7/2/2013    
DetailsSam Zahorka