Permit Information
Permit NumberGCB13-00100
StatusFinaled
Name Design Resources PLLC
Site Address 4902 CHINDEN BLVD
Project NameBLD2013-00098
Customer Number 
ePlanReviewNo
Description
Vineyard Christian Fellowship TI - **3-7-14 PLAN MODIFICATION TO INCLUDE REMOVE AND REPLACE TWO EXISTING EXTERIOR WINDOWS WITH NEW DOUBLE LEAF DOORS WITH NEW DOOR HARDWARE. SRZ** To remodel an existing 3,128 square foot building for a non-separated mixed use/occupancy for food distribution and assembly occupancy. Work to include: construct new interior walls and associated doors to create a new assembly and distribution room, four new conference rooms, and new assembly and packaging room; remove an existing exterior door and replace with new double doors; install new exterior aluminum windows; new exterior manufactured stone veneer in locations per plans; construct new exterior canopy/fascia’s and columns over the new entry locations per plans; related interior finishes in compliance with chapter 8 of the 2009 IBC; and electrical work. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. The Assembly/Distibution room shall be posted with a Max. occupant load of 60 persons. The Assembly/Packaging room shall be posted with a Max. occupant load of 64 persons. NOTE: This building is NOT fire sprinklered. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final10/22/201410/23/201410/23/2014PPASS
DetailsTony Young
Steve ###-####,, ok pending others
GCB-Footing4/28/20144/29/20144/29/2014APASS
DetailsMike Jordan
Ken ###-####. Column pad footings for new canopy at main enterance. Noted to contractor that special inspection may be required if design strength is greater that 2500psi. Noted to contractor to either get verification from engineer of record or have concrete tested.
Plan assigned to (SRZ)1/24/20141/24/20143/11/2014 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/11/2014 DONE
DetailsSam Zahorka
Issue and Courier  3/11/2014 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK1/24/2014 3/11/2014 PASS
DetailsSam Zahorka
GCB-Framing2/24/20142/25/20142/25/2014APART
DetailsTom Arcoraci
Steven ###-#### please call half hour before for access ok to cover int walls after elec insp
Plan resubmittals received  1/24/2014 DONE
DetailsChristina Prado
Received three sets of revised plan sheets marked A1.1, A2.1 & A7.2; Taken to Sam for further review
Issue and Courier  11/15/2013 DONE
DetailsBarbara Stitt
Plan assigned to (SRZ)7/22/20137/22/201311/14/2013 DONE
DetailsSam Zahorka
3rd review completed.
Routing - PLAN CHECK11/1/2013 11/14/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  11/14/2013 DONE
DetailsSam Zahorka
Routing - PLAN CHECK11/1/2013 11/1/2013 PEND
DetailsSam Zahorka
Pending letter from the applicant detailing accessible route upgrades and operation procedures.
Plan resubmittals received  10/31/2013  
Received 3 copies of sheets A0.1, A1.1, A2.1, A3.1, A7.1, A7.2, L1.1, L1.2 and taken to Sam Zahorka's desk
Routing - PLAN CHECK10/4/2013 10/4/2013 FAIL
DetailsSam Zahorka
Plan resubmittals received  10/3/2013  
Received 3 copies of structural calcs, 3 copies of sheets A1.1, A2.1, A7.1, A7.2, S1.1, S1.2 and taken to Sam's desk
Routing - PLAN CHECK7/23/2013 8/8/2013 FAIL
DetailsSam Zahorka
Sam Zahorka
1st review completed  8/8/2013 DONE
DetailsSam Zahorka
Routing - Mechanical Review7/22/2013 7/23/2013 PASS
DetailsTroy James
field verify mechanical ventilation to new conference rooms
Application received  7/17/2013 DONE