Plan resubmittals received | | | 2/3/2014 | | DONE |
|
|
|
new manual j report
|
Routing - Mechanical Review | 2/3/2014 | | 2/3/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
GCB-Final | 1/30/2014 | 1/30/2014 | 1/30/2014 | P | PASS |
Mike Jordan
|
|
|
Chad ###-####. Structural final only ok.
|
GCB-Final | 1/29/2014 | 1/29/2014 | 1/29/2014 | P | NR |
Dave Hannah
|
|
|
Chad ###-#### call first for access needs a blower door test and energy cert
|
GCB-Energy | 10/15/2013 | 10/15/2013 | 10/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
Chad ###-####
|
Plan resubmittals received | | | 10/14/2013 | | DONE |
|
|
|
new manual j
|
Routing - Mechanical Review | 10/14/2013 | | 10/14/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
CHANGE STATUS TO (ISS) | | | 10/14/2013 | | DONE |
|
|
|
|
GCB-Framing | 10/10/2013 | 10/10/2013 | 10/10/2013 | P | PASS |
Jim Sly
|
|
|
Chad ###-####
|
GCB-Shearwall | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PASS |
Jim Sly
|
|
|
Chad ###-####
|
GCB-Fndatn/slab ins/fld vent | 8/23/2013 | 8/23/2013 | 8/23/2013 | P | PASS |
Dave Hannah
|
|
|
Ben ###-####
|
GCB-Footing | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PASS |
Mike Jordan
|
|
|
Jay ###-####
|
Issue and Courier | | | 7/31/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 7/29/2013 | 7/29/2013 | 7/30/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 7/29/2013 | | 7/30/2013 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
1st review completed | | | 7/30/2013 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 7/29/2013 | | 7/29/2013 | | PASS |
Troy James
|
|
|
|
Application received | | | 7/25/2013 | | DONE |
|
|
|
|