Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberGCB13-00146
StatusFinaled
Name RIVERSIDE HOMES
Site Address 426 E WATER POCKET
Project NameBLD2013-00144
Customer Number 
ePlanReviewNo
Description
To construct a new 2,436 square foot, Three story (1,065 square foot 1st story / 962 square foot 2nd story / 409 square foot 3rd story), three bedroom, two full bath, two half bath, single family dwelling with a 586 square foot attached garage, and a 210 square foot covered patio. All work per the approved plans, attached plan review report, engineering, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. ENGINEERED DESIGN FOR SHEAR WALLS PER DESIGN PROFESSIONAL. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final2/19/20142/20/20142/20/2014APASS
DetailsTom Arcoraci
###-#### blower door test pass strucural final ok
GCB-Final2/14/20142/18/20142/18/2014PFAIL
DetailsJim Sly
Pete ###-#### call for access
Need verification of approval Foam seal or Blower door test.
GCB-Energy12/20/201312/20/201312/20/2013PPASS
DetailsMike Jordan
All framing have been resolved as well.
GCB-Energy12/19/201312/20/201312/20/2013ACANC
DetailsMike Jordan
Chee ###-####. Moved to pm inspection.
GCB-Framing12/18/201312/19/201312/19/2013PFAIL
DetailsMike Jordan
Chee ###-####. Provide squash blocking under 2nd. floor framing for paralam above to transfer loads. Tighten holddown at5 east wall. Justify openings in inter shear panels. ok to insulate.
Miscellaneous Hourly  12/9/2013 DONE
New manual j report submitted for review.
GCB-Ceiling Grid12/5/201312/6/201312/6/2013PPASS
DetailsJim Sly
###-#### Chee (call first)
Rock on Ext. soffits.....OK.
GCB-Shearwall12/4/201312/5/201312/5/2013APART
DetailsJim Sly
Chee ###-#### Call first
Exterior strapping and nailing only....OK. Need to verify nuts on HDs....and interior shear wall/nailing OK.
GCB-Fndatn/slab ins/fld vent11/7/201311/7/201311/7/2013PPASS
DetailsTony Young
Nate ###-####
GCB-Footing11/6/201311/6/201311/7/2013PPASS
DetailsDave Hannah
Nate ###-#### Concrete pour at 4:00, please inspect footings prior
Plan assigned to (SRZ)10/17/201310/17/201311/4/2013 DONE
DetailsSam Zahorka
1st review completed.
Routing - PLAN CHECK11/1/2013 11/4/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  11/4/2013 DONE
DetailsSam Zahorka
Issue and Courier  11/4/2013 DONE
DetailsBarbara Stitt
Plan resubmittals received  11/1/2013 DONE
DetailsChristina Prado
Received three sets of revised plan sheets marked 1,2,3,4,5,6 & 7
1st review completed  10/28/2013 DONE
DetailsSam Zahorka
Routing - PLAN CHECK10/17/2013 10/28/2013 FAIL
DetailsSam Zahorka
Sam Zahorka
Routing - Mechanical Review10/18/2013 10/18/2013 PASS
DetailsTroy James
Routing - Mechanical Review10/17/2013 10/17/2013 FAIL
DetailsTroy James
emailed corrections to Legend heating
Application received  10/15/2013 DONE