GCB-Final | 8/11/2014 | 8/11/2014 | 8/11/2014 | P | PASS |
Phil Shearer
|
|
|
willie ###-#### garage 3484 "enter" Structural final only OK
|
GCB-Energy | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | PASS |
Mike Jordan
|
|
|
Willie ###-####
|
GCB-Framing | 12/30/2013 | 12/30/2013 | 12/30/2013 | P | PASS |
Tony Young
|
|
|
Willie ###-####,, ok to insulate
|
GCB-Shearwall | 12/19/2013 | 12/19/2013 | 12/19/2013 | P | PASS |
Mike Jordan
|
|
|
Willie ###-####
|
GCB-Shearwall | 12/16/2013 | 12/16/2013 | 12/16/2013 | P | FAIL |
Mike Jordan
|
|
|
Willie ###-####. install all missing blocking, nail off. complete all let in bracing and interior wall bracing.
|
GCB-Fndatn/slab ins/fld vent | 11/22/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Jim Sly
|
|
|
Heron ###-#### Jim, please record inspection results from this morning
|
GCB-Footing | 11/13/2013 | 11/14/2013 | 11/14/2013 | A | PASS |
Dave Hannah
|
|
|
Heron ###-####
|
Issue and Courier | | | 11/1/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 10/24/2013 | 10/24/2013 | 10/31/2013 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - Mechanical Review | 10/24/2013 | | 10/31/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 10/31/2013 | | 10/31/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/28/2013 | | 10/28/2013 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
Application received | | | 10/22/2013 | | DONE |
|
|
|
|