GCB-Final | 3/27/2014 | 3/28/2014 | 3/28/2014 | A | PASS |
Dave Hannah
|
|
|
project manager Sandy Irvine ###-#### final for permanent C of O
|
GCB-Final | 1/15/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Mike Jordan
|
|
|
GCB-Final 1/10/2014 1/10/2014 1/10/2014 P PART DetailsMike Jordan temp occupanvy for structural final only. Will be ok for perm occ. once other trades sign from temp. to perm occ. Structural final only ok. Cannot verify other trades finals.
|
GCB-Final | 1/10/2014 | 1/10/2014 | 1/10/2014 | P | PART |
Mike Jordan
|
|
|
temp occupanvy for structural final only. Will be ok for perm occ. once other trades sign from temp. to perm occ.
|
GCB-Ceiling Grid | 1/9/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Mike Jordan
|
|
|
Steve ###-####. ceiling gid inspected yesterday on bldg. conferance. no time. Will be ready for final inspection in pm. per contractor.
|
GCB-Framing | 1/8/2014 | 1/9/2014 | 1/9/2014 | P | DONE |
Mike Jordan
|
|
|
Steve ###-####
|
GCB-Framing | 12/26/2013 | 12/26/2013 | 12/26/2013 | P | PART |
Jim Sly
|
|
|
Steve ###-#### restrooms only Hard ceiling at restrooms and hall.....OK.
|
GCB-Framing | 12/18/2013 | 12/18/2013 | 12/18/2013 | P | PART |
Mike Jordan
|
|
|
Added inspection. Incorrect time on last inspection.
|
GCB-Framing | 12/17/2013 | 12/18/2013 | 12/18/2013 | A | PART |
Mike Jordan
|
|
|
Steve ###-#### This is on back bathroom wall. Does not have the required min 42'' clear width in hallway between restrooms. Will reframe the non structural bathroom wall, replacing the steel studs with 2x4 framed wall to gain the requied clear width.
|
GCB-Framing | 12/12/2013 | 12/13/2013 | 12/13/2013 | P | PASS |
Mike Jordan
|
|
|
PM please. interior steel stud walls, no restrooms. Needs to resubmit to show additional office at west side of bldg. and show door to hallway comply with ada.
|
Issue and Courier | | | 12/2/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 11/14/2013 | 11/14/2013 | 11/27/2013 | | DONE |
Sam Zahorka
|
|
|
1st review completed. JD BYRIDER AUTO SALES
|
Plan resubmittals received | | | 11/27/2013 | | |
|
|
|
Received 2 copies of sheets M0.1, E2.2 and taken to Sam Zahorka's desk
|
Routing - PLAN CHECK | 11/27/2013 | | 11/27/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/15/2013 | | 11/25/2013 | | FAIL |
Sam Zahorka
|
|
|
1st review completed.
|
1st review completed | | | 11/25/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 11/14/2013 | | 11/15/2013 | | PASS |
Troy James
|
|
|
|
Application received | | | 11/12/2013 | | DONE |
|
|
|
|