Case Summary (GCB) | | | 10/22/2014 | | DONE |
|
|
|
|
GCB-Final | 7/11/2014 | 7/11/2014 | 7/14/2014 | P | DONE |
Dave Hannah
|
|
|
Mix-up on inspection type, Dave Hannah able to inspect
|
GCB-Final | 7/11/2014 | 7/11/2014 | 7/11/2014 | P | PASS |
Dave Hannah
|
|
|
|
GCB-Fndatn/slab ins/fld vent | 7/11/2014 | 7/11/2014 | 7/11/2014 | P | CANC |
Dave Hannah
|
|
|
per Dave Hannah
|
GCB-Footing | 6/6/2014 | 6/9/2014 | 6/9/2014 | P | PASS |
Dave Hannah
|
|
|
Final Footings inspection for front unit. richard ###-#### front building only, verify on approved plans wood stem wall ok to cover
|
GCB-Fndatn/slab ins/fld vent | 5/30/2014 | 6/2/2014 | 6/2/2014 | A | PART |
Dave Hannah
|
|
|
richard ###-#### front building only, verify on approved plans ok to grout cmu foundation wall
|
GCB-Footing | 5/22/2014 | 5/23/2014 | 5/23/2014 | A | PASS |
Dave Hannah
|
|
|
Richard ###-#### or ###-#### only front unit is permitted for foundation, verify with plans
|
Plan assigned to (SRZ) | 1/14/2014 | 1/14/2014 | 3/24/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Plan resubmittals received | | | 3/24/2014 | | DONE |
Sam Zahorka
|
|
|
Revised foundation plans received via email from Garden City.
|
Routing - PLAN CHECK | 3/24/2014 | | 3/24/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 3/24/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 1/14/2014 | | 1/17/2014 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
1st review completed | | | 1/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
Application received | | | 1/13/2014 | | DONE |
|
|
|
|