GCB-Final | 5/21/2014 | 5/22/2014 | 5/22/2014 | A | PASS |
Jim Sly
|
|
|
acess code please call with any questions ###-#### Structural final only...... OK.
|
Plan resubmittals received | | | 5/2/2014 | | DONE |
|
|
|
new manual j
|
Routing - Mechanical Review | 5/2/2014 | | 5/2/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
GCB-Energy | 3/31/2014 | 4/1/2014 | 4/1/2014 | P | PASS |
Tom Arcoraci
|
|
|
GREY ###-####
|
GCB-Framing | 3/28/2014 | 3/31/2014 | 3/31/2014 | A | PASS |
Jim Sly
|
|
|
Grey ###-#### Called cotntr....... Just need 4 nuts/washers on anchor bolts....Front wall.
|
GCB-Shearwall | 3/21/2014 | 3/24/2014 | 3/24/2014 | A | PASS |
Tom Arcoraci
|
|
|
Greg ###-####
|
GCB-Energy | 3/11/2014 | 3/12/2014 | 3/12/2014 | P | PASS |
Jim Sly
|
|
|
greg ###-#### energy inspection for insulation for foundation (slab)
|
GCB-Fndatn/slab ins/fld vent | 3/5/2014 | 3/5/2014 | 3/5/2014 | P | PASS |
Jim Sly
|
|
|
Ben ###-####
|
GCB-Footing | 3/3/2014 | 3/4/2014 | 3/4/2014 | P | PASS |
Jim Sly
|
|
|
Grey ###-####
|
Plan assigned to (SRZ) | 1/17/2014 | 1/17/2014 | 2/21/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - PLAN CHECK | 2/21/2014 | | 2/21/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 2/21/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/20/2014 | | DONE |
Christina Prado
|
|
|
received one response letter as well as three sets of revised plan sheets marked A1.0, A1.1, A1.4, A2.0, A3.0, A5.0 & A5.2; Plans taken to Sam for further review
|
Routing - PLAN CHECK | 1/22/2014 | | 1/30/2014 | | FAIL |
Sam Zahorka
|
|
|
Sam Zahorka
|
1st review completed | | | 1/30/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 1/17/2014 | | 1/22/2014 | | PASS |
Troy James
|
|
|
|
Application received | | | 1/15/2014 | | DONE |
|
|
|
|