Permit Information
Permit NumberGCB14-00015
StatusFinaled
Name French Homes Inc.
Site Address 472 E 51ST
Project NameBLD2014-00015
Customer Number 
ePlanReviewNo
Description
(Lot 9 Townhome) - To construct a new 2,936 square foot, Two story, Four bedroom, two and a half bathroom, single family dwelling townhouse with a 416 square foot attached garage, a 48 square foot covered front patio, and a 48 square foot covered rear patio. All work per the approved plans, attached plan review report, Engineering, and all other reviewing agencies approvals. 1-hour fire-resistance construction is required on all projections closer than 3 feet to the property line. Distance to property line for fire rated construction is measured from the finished exterior of the exterior wall. Any walls less than 3' from the property line are required to have 1-hour fire-resistance construction. This structure is located in the floodplain. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final8/27/20148/28/20148/28/2014APASS
DetailsMike Jordan
Dan ###-####. All issues resolved. Structural final ok.
GCB-Final8/26/20148/27/20148/27/2014PFAIL
DetailsMike Jordan
Dan ###-####. Handrail at top of stairs needs to return into wall. Firecaulk wires from garage door opener at garage lid. Provide blower door test results or 3rd party airseal inspection report and post. Coorection notice issued and posted on electrical panel in garage.
CHANGE STATUS TO (ISS)  8/27/2014 DONE
DetailsSam Zahorka
GCB-Framing6/13/20146/13/20146/19/2014PDEFR
DetailsDave Hannah
Dan ###-#### plans in fireplace at 460 51st
GCB-Energy6/13/20146/13/20146/19/2014PDEFR
DetailsDave Hannah
Dan ###-#### plans in fireplace at 460 51st
GCB-Framing6/17/20146/17/20146/17/2014PCANC
DetailsMike Jordan
Dan ###-#### plans in fireplace at 46 East 51st
GCB-Energy6/17/20146/17/20146/17/2014PPASS
DetailsMike Jordan
Dan ###-#### plans in fireplace at 460 E 51st
GCB-Framing6/11/20146/12/20146/12/2014PPASS
DetailsDave Hannah
DAN FRENCH ###-####
Plan resubmittals received  6/10/2014 DONE
new manual j
Routing - Mechanical Review6/10/2014 6/10/2014 PASS
DetailsTroy James
resubmitted manual j
GCB-Courtesy5/20/20145/21/20145/22/2014PDONE
DetailsJim Sly
Dan French ###-#### call to meet onsite to discuss sheetrock adjacent ot two hour firewall
GCB-Framing5/19/20145/20/20145/20/2014PPASS
DetailsJim Sly
Dan French ###-####
GCB-Shearwall5/2/20145/2/20145/2/2014PPASS
DetailsTom Arcoraci
Dan ###-#### re-inspect
GCB-Shearwall4/30/20145/1/20145/1/2014PFAIL
DetailsMike Jordan
Dan 602.3255. Please provide approved plans. Also provide 5/8type x rock at soffits at 2hr. firewalls. Correction notice posted.
GCB-Fire Wall4/9/20144/9/20144/9/2014PPASS
DetailsMike Jordan
Dan ###-#### first layer on, check nailing before second layer. Base layer, 1st. floor ok.
GCB-Footing3/12/20143/12/20143/12/2014PPASS
DetailsJim Sly
Plan assigned to (SRZ)2/4/20142/4/20142/18/2014 DONE
DetailsSam Zahorka
1st review completed. Corrections needed.
Routing - PLAN CHECK2/14/2014 2/18/2014 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  2/18/2014 DONE
DetailsSam Zahorka
Issue and Courier  2/18/2014 DONE
DetailsChristina Prado
Plan resubmittals received  2/14/2014  
Received 3 copies of Elevations sheet and Roof framing sheet and taken to Sam Zahorka's desk
Routing - PLAN CHECK2/7/2014 2/11/2014 FAIL
DetailsSam Zahorka
Sam Zahorka
1st review completed  2/11/2014 DONE
DetailsSam Zahorka
Routing - Mechanical Review2/4/2014 2/7/2014 PASS
DetailsTroy James
Application received  2/3/2014 DONE