Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberGCB14-00019
StatusFinaled
Name BRS Architects
Site Address 8695 W MARIGOLD ST
Project NameBLD2014-00019
Customer Number 
ePlanReviewNo
Description
(Boise Bible College - Student Union Building) To construct a new 7,295 square foot, two story Student Union/Assembly building addition (4,129 square foot 1st story / 3,000 square foot 2nd story). The 1st story floor will be concrete slab on grade; The exterior walls will be wood light frame construction; The interior walls will also be wood light frame construction; The roof will be pre-engineered with wood sheathing and asphalt shingle roof system; Upper floor system to be wood joist with a concrete topping slab over. All work shall comply with the approved drawings, the plan review report, and all applicable codes. This project will be connected to an existing two story girls dorm building that has an existing 2-hour fire wall with protected openings. This existing 2-hour Fire wall will separate the existing girls dorm building from this new Student Union building. This building will receive an automatic fire sprinkler system for occupancy and for story increase. The fire sprinkler system shall be per NFPA 13 as regulated by the fire department. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final10/15/201410/16/201410/16/2014PPASS
DetailsJim Sly
Jessee or Ron at ###-####
GCB-Final10/15/201410/15/201410/15/2014PCANC
DetailsJim Sly
Jessie ###-#### or Ron ###-####
Contr. scheduled for the next day.
GCB-Energy8/6/20148/7/20148/7/2014PPASS
DetailsPhil Shearer
please call prior to inspection
GCB-Framing7/31/20148/1/20148/1/2014APASS
DetailsDave Hannah
Jesse ###-#### please call to meet on-site
GCB-Shearwall7/1/20147/2/20147/2/2014APASS
DetailsTony Young
Ron ###-####,, exterior ok
GCB-Shearwall6/30/20147/1/20147/1/2014AFAIL
DetailsDave Hannah
Ron ###-#### please call first; shearnail inspection request crew used stapels plans call for nails
GCB-Assembly5/12/20145/13/20145/13/2014APASS
DetailsMike Jordan
Jesse ###-#### nailing inspection requestedbase and face layers of 5/8 type x rock for 2hr. firewall, 1st. floor at existing building. Shearwall nailing for new walls at existing building, 1st. floor.
GCB-Footing5/2/20145/5/20145/5/2014APASS
DetailsMike Jordan
Jessie ###-####. Interior footings and exterior north footing line ok.
Plan assigned to (SRZ)3/4/20143/4/20144/22/2014 DONE
DetailsSam Zahorka
Pending Structural Review to PASS.
Routing Off Site - STRUCTURAL4/17/2014 4/22/2014 PASS
DetailsSam Zahorka
Routing - PLAN CHECK4/22/2014 4/22/2014 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  4/22/2014 DONE
DetailsSam Zahorka
Issue and Courier  4/22/2014 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK4/17/2014 4/21/2014 PEND
DetailsSam Zahorka
Pending Structural to PASS.
Telephone call  4/17/2014 DONE
DetailsChristina Prado
called Action Couriers for pick up
Routing Off Site - STRUCTURAL3/21/2014 4/3/2014 FAIL
DetailsSam Zahorka
1st review completed  3/28/2014 DONE
DetailsSam Zahorka
Telephone call  3/28/2014 DONE
DetailsSam Zahorka
Called Garden CIty and the Architect to let them know 1st review is pending structural plan review comments.
Routing - PLAN CHECK3/7/2014 3/28/2014 FAIL
DetailsSam Zahorka
Routing - Mechanical Review3/4/2014 3/7/2014 PASS
DetailsTroy James
Application received  2/24/2014 DONE
Plan resubmittals received    
Received 2 copies of cover transmittal, 1copy of structural plan trview comments from Stapley, 1 copy of plan review comments from BRS Architects, 1 copy of pla review comments from Engineering Conslutants, 2 copies of Structural Cals, 3 copies of statement of special inspections, 2 copies of HVAC Load anslysis, 4 sets of sheets G-1, A0.1, A3.1, A7.1, A10.1, C1.2, S0.1, S5.1, P1.1, EC.1 and taken to Sam Zahorka's desk