GCB-Final | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Mike Jordan
|
|
|
Willy ###-####. Structural final only ok.
|
GCB-Energy | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PASS |
Jim Sly
|
|
|
Willy ###-####
|
GCB-Framing | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | PASS |
Jim Sly
|
|
|
Willie ###-####
|
GCB-Shearwall | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | PASS |
Tom Arcoraci
|
|
|
Willie ###-####
|
GCB-Shearwall | 4/29/2014 | 4/30/2014 | 4/30/2014 | A | FAIL |
Mike Jordan
|
|
|
Willie ###-####. Wall bracing not completed, and over spaced. Will complete, restaple and call for reinspection.
|
GCB-Stem wall | 4/9/2014 | 4/10/2014 | 4/10/2014 | P | PART |
Tony Young
|
|
|
Adam ###-#### 2PM please.. work in progress,, ok
|
GCB-Stem wall | 4/8/2014 | 4/9/2014 | 4/9/2014 | P | CANC |
Tony Young
|
|
|
adam ###-#### called in for a foundation wall inspection. looking for a 3PM inspection
|
GCB-Footing | 4/7/2014 | 4/8/2014 | 4/8/2014 | P | PART |
Tony Young
|
|
|
Adam ###-#### plan to pour at 4PM,, work in progress,,
|
GCB-Fndatn/slab ins/fld vent | 4/1/2014 | 4/3/2014 | 4/3/2014 | P | NR |
Mike Jordan
|
|
|
###-####. No one on site. Pad is excavated. No forms or property lines in place. Will need to reschedule.
|
GCB-Footing | 4/1/2014 | 4/2/2014 | 4/2/2014 | P | NR |
Dave Hannah
|
|
|
###-####
|
Plan assigned to (SRZ) | 3/6/2014 | 3/6/2014 | 3/12/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/11/2014 | | 3/12/2014 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 3/12/2014 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 3/12/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Mechanical Review | 3/6/2014 | | 3/11/2014 | | PASS |
Troy James
|
|
|
|
Application received | | | 3/4/2014 | | DONE |
|
|
|
|