Permit Information
Permit NumberGCB14-00020
StatusFinaled
Name Red Oak Development
Site Address 6414 N MYSTIC COVE
Project NameBLD2014-00020
Customer Number 
ePlanReviewNo
Description
To construct a new 1,995 square foot, two story (1,325 square foot 1st story / 670 square foot 2nd story), three bedroom, two and half bathrooms, single family dwelling with a 463 square foot attached garage, a 18 square foot covered porch, and a 69 square foot covered side patio. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. FEMA (LOMR-F) noted on plans removing this property from the floodplain. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final7/24/20147/25/20147/25/2014APASS
DetailsMike Jordan
Willy ###-####. Structural final only ok.
GCB-Energy5/19/20145/20/20145/20/2014APASS
DetailsJim Sly
Willy ###-####
GCB-Framing5/14/20145/14/20145/14/2014PPASS
DetailsJim Sly
Willie ###-####
GCB-Shearwall5/1/20145/2/20145/2/2014APASS
DetailsTom Arcoraci
Willie ###-####
GCB-Shearwall4/29/20144/30/20144/30/2014AFAIL
DetailsMike Jordan
Willie ###-####. Wall bracing not completed, and over spaced. Will complete, restaple and call for reinspection.
GCB-Stem wall4/9/20144/10/20144/10/2014PPART
DetailsTony Young
Adam ###-#### 2PM please.. work in progress,, ok
GCB-Stem wall4/8/20144/9/20144/9/2014PCANC
DetailsTony Young
adam ###-#### called in for a foundation wall inspection. looking for a 3PM inspection
GCB-Footing4/7/20144/8/20144/8/2014PPART
DetailsTony Young
Adam ###-#### plan to pour at 4PM,, work in progress,,
GCB-Fndatn/slab ins/fld vent4/1/20144/3/20144/3/2014PNR
DetailsMike Jordan
###-####. No one on site. Pad is excavated. No forms or property lines in place. Will need to reschedule.
GCB-Footing4/1/20144/2/20144/2/2014PNR
DetailsDave Hannah
###-####
Plan assigned to (SRZ)3/6/20143/6/20143/12/2014 DONE
DetailsSam Zahorka
Routing - PLAN CHECK3/11/2014 3/12/2014 PASS
DetailsSam Zahorka
1st review completed  3/12/2014 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/12/2014 DONE
DetailsSam Zahorka
Issue and Courier  3/12/2014 DONE
DetailsBarbara Stitt
Routing - Mechanical Review3/6/2014 3/11/2014 PASS
DetailsTroy James
Application received  3/4/2014 DONE