GCB-Final | 8/21/2014 | 8/22/2014 | 8/22/2014 | A | PASS |
Dave Hannah
|
|
|
Chad ###-#### call ahead please
|
GCB-Final | 8/21/2014 | 8/21/2014 | 8/21/2014 | A | NH |
Dave Hannah
|
|
|
doors are lock no number to call
|
GCB-Energy | 6/17/2014 | 6/17/2014 | 6/17/2014 | P | PASS |
Tom Arcoraci
|
|
|
Chad ###-####
|
GCB-Framing | 6/16/2014 | 6/17/2014 | 6/17/2014 | A | PASS |
Jim Sly
|
|
|
BOB ###-####
|
GCB-Framing | 6/12/2014 | 6/13/2014 | 6/13/2014 | A | FAIL |
Mike Jordan
|
|
|
Bob ###-#### please call 45 minutes prior to meet on site. Needs electrical rough in inspection.
|
GCB-Shearwall | 6/6/2014 | 6/9/2014 | 6/9/2014 | A | PASS |
Jim Sly
|
|
|
Bob ###-####
|
GCB-Footing | 6/3/2014 | 6/4/2014 | 6/4/2014 | A | CANC |
Tom Arcoraci
|
|
|
|
GCB-Courtesy | 6/2/2014 | 6/3/2014 | 6/3/2014 | A | DONE |
Mike Jordan
|
|
|
questions on headroom at stairs.
|
GCB-Footing | 5/21/2014 | 5/21/2014 | 5/22/2014 | P | PASS |
Jim Sly
|
|
|
Heron phone###-####
|
GCB-Footing | 5/20/2014 | 5/21/2014 | 5/21/2014 | A | CANC |
Jim Sly
|
|
|
Norm ###-####
|
Plan assigned to (SRZ) | 5/13/2014 | 5/13/2014 | 5/19/2014 | | DONE |
Sam Zahorka
|
|
|
Pending Mechanical to PASS.
|
Routing - Mechanical Review | 5/19/2014 | | 5/19/2014 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 5/19/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Mechanical Review | 5/13/2014 | | 5/15/2014 | | FAIL |
Troy James
|
|
|
Plan Modifications. emailed corrections to building energy
|
Plan resubmittals received | | | 5/13/2014 | | |
|
|
|
Reeived 1 copy of sheets Site, 1 of 7, 2 of 7, 3 of 7, 4 of 7, 5 of 7, 6 of 7, 7 of 7 and taken to Sam Zahorka's desk
|
Routing - PLAN CHECK | 5/13/2014 | | 5/13/2014 | | PASS |
Sam Zahorka
|
|
|
Plan Modifications.
|
Plan resubmittals received | | | 5/13/2014 | | |
|
|
|
Received 3 sets of sheets SITE, 1 of 7, 2 of 7, 3 of 7, 4 of 7, 5 of 7, 6 of 7 , 7 of 7, 1 res check, 1 manual J, and taken to Sam Zahorka's desk
|
GCB-Footing | 4/11/2014 | 4/14/2014 | 4/15/2014 | P | PASS |
Jim Sly
|
|
|
|
Plan assigned to (SRZ) | 3/28/2014 | 3/28/2014 | 4/7/2014 | | DONE |
Sam Zahorka
|
|
|
Pending Designer to call back concerning Wall Bracing
|
Routing - PLAN CHECK | 4/3/2014 | | 4/7/2014 | | PEND |
Sam Zahorka
|
|
|
Waiting for the desiger to call me back concerning the wall bracing question.
|
Routing - PLAN CHECK | 4/7/2014 | | 4/7/2014 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 4/7/2014 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/7/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 4/7/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Mechanical Review | 3/28/2014 | | 4/3/2014 | | PASS |
Troy James
|
|
|
|
Application received | | | 3/27/2014 | | DONE |
|
|
|
|