Permit Information
Permit NumberGCB14-00055
StatusFinaled
Name BRSARCHITECTS
Site Address 4983 N GLENWOOD ST
Project NameBLD2014-00054
Customer Number 
ePlanReviewNo
Description
Revolutions TI - To remodel the interior of this existing building and increase the current tenants area by occupying an existing office area. Work to include: cut a new opening in the existing 3 hour Fire Barrier wall for access to the new tenant areas; provide a new 3-hour fire door with closer, smoke seal and door hardware; construct a metal stud wall to separate the concession area from the new office area; install new double doors and associated hardware at the new office room entry location; install new emergency illuminated exit signage; related interior finishes in compliance with chapter 8 of the 2012 IBC; and all other work per approved plans, attached plan review report, and all reviewing agencies approvals. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved. NOTE: This building is fully fire sprinklered for area increase. All alterations and modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
GCB-Final7/20/20157/21/20157/22/2015APASS
DetailsDave Hannah
Justin Anderson ###-#### - requested call ahead
GCB-Final7/21/20157/22/20157/22/2015APASS
DetailsDave Hannah
Justin ###-#### - requested call ahead
GCB-Final7/9/20157/9/20157/9/2015PFAIL
DetailsMike Jordan
Creston ###-#### - requested 15min call ahead. Provide smoke seal and tag frame.
FIRE-Final Inspection7/9/20157/9/20157/9/2015PPASS
DetailsKatie Marron
Life Safety pass pending new fire extinguisher in additional space, and replacing batteries in three emergency lights on upper hallway. Items to be corrected prior to bld inspection.
Plan assigned to (SRZ)5/29/20145/29/201412/15/2014 DONE
DetailsSam Zahorka
3rd review completed.
PLANS/APPL TAKEN TO FRONT DESK  12/15/2014 DONE
DetailsSam Zahorka
Issue and Courier  12/15/2014 DONE
DetailsCandy A. Nichols
Building Official Hourly  12/12/2014 DONE
DetailsJason Blais
1 hour of Building Official time added to the case to approve the alternate request.
Routing - FIRE12/5/201412/5/201412/11/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 12-11-14
Routing - PLAN CHECK12/11/2014 12/11/2014 PASS
DetailsSam Zahorka
Routing - PLAN CHECK12/2/2014 12/5/2014 PEND
DetailsSam Zahorka
Pending Alternate to be approved.
Plan resubmittals received  12/2/2014 DONE
DetailsCandy A. Nichols
Received 1 transmittal sheet and 3 each sheet G1, response letter from BRS-took to Sam Z
Routing - PLAN CHECK12/1/2014 12/1/2014 FAIL
DetailsSam Zahorka
Telephone call  12/1/2014 DONE
DetailsSam Zahorka
Called the architect Joe Thompson and went over the corrections needed prior to issuing the permit. Occupant loads and square footages need to match on all plan sheets and alternate request letter and attachments.
Plan resubmittals received  11/18/2014 DONE
DetailsCandy A. Nichols
received 3 sets of each: sheet G1, response emails to Jason B & Sam Z - took to Sam Z
Routing - PLAN CHECK10/28/2014 11/3/2014 FAIL
DetailsSam Zahorka
Routing - FIRE5/29/20145/29/20146/19/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 06-19-14
1st review completed  6/19/2014 DONE
DetailsSam Zahorka
Routing - PLAN CHECK6/3/2014 6/18/2014 FAIL
DetailsSam Zahorka
Routing - Public Works5/29/20145/29/20146/2/2014 PASS
DetailsBeverly Mountain
Application received  5/27/2014 DONE