GCB-Final | 7/20/2015 | 7/21/2015 | 7/22/2015 | A | PASS |
Dave Hannah
|
|
|
Justin Anderson ###-#### - requested call ahead
|
GCB-Final | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Dave Hannah
|
|
|
Justin ###-#### - requested call ahead
|
GCB-Final | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | FAIL |
Mike Jordan
|
|
|
Creston ###-#### - requested 15min call ahead. Provide smoke seal and tag frame.
|
FIRE-Final Inspection | 7/9/2015 | 7/9/2015 | 7/9/2015 | P | PASS |
Katie Marron
|
|
|
Life Safety pass pending new fire extinguisher in additional space, and replacing batteries in three emergency lights on upper hallway. Items to be corrected prior to bld inspection.
|
Plan assigned to (SRZ) | 5/29/2014 | 5/29/2014 | 12/15/2014 | | DONE |
Sam Zahorka
|
|
|
3rd review completed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/15/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 12/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Building Official Hourly | | | 12/12/2014 | | DONE |
Jason Blais
|
|
|
1 hour of Building Official time added to the case to approve the alternate request.
|
Routing - FIRE | 12/5/2014 | 12/5/2014 | 12/11/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 12-11-14
|
Routing - PLAN CHECK | 12/11/2014 | | 12/11/2014 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 12/2/2014 | | 12/5/2014 | | PEND |
Sam Zahorka
|
|
|
Pending Alternate to be approved.
|
Plan resubmittals received | | | 12/2/2014 | | DONE |
Candy A. Nichols
|
|
|
Received 1 transmittal sheet and 3 each sheet G1, response letter from BRS-took to Sam Z
|
Routing - PLAN CHECK | 12/1/2014 | | 12/1/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Telephone call | | | 12/1/2014 | | DONE |
Sam Zahorka
|
|
|
Called the architect Joe Thompson and went over the corrections needed prior to issuing the permit. Occupant loads and square footages need to match on all plan sheets and alternate request letter and attachments.
|
Plan resubmittals received | | | 11/18/2014 | | DONE |
Candy A. Nichols
|
|
|
received 3 sets of each: sheet G1, response emails to Jason B & Sam Z - took to Sam Z
|
Routing - PLAN CHECK | 10/28/2014 | | 11/3/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 5/29/2014 | 5/29/2014 | 6/19/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 06-19-14
|
1st review completed | | | 6/19/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/3/2014 | | 6/18/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Public Works | 5/29/2014 | 5/29/2014 | 6/2/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 5/27/2014 | | DONE |
|
|
|
|