GCB-Final | 9/23/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Dave Hannah
|
|
|
Manny ###-####
|
FIRE-Final Inspection | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PASS |
Craig D. Hanson
|
|
|
|
GCB-Final | 9/17/2014 | 9/18/2014 | 9/18/2014 | P | NR |
Dave Hannah
|
|
|
Manie ###-#### needs fire finals and vest.
|
GCB-Ceiling Grid | 9/12/2014 | 9/15/2014 | 9/15/2014 | A | PASS |
Dave Hannah
|
|
|
did not leave a number/name
|
GCB-Ceiling Grid | 9/10/2014 | 9/11/2014 | 9/11/2014 | P | FAIL |
Dave Hannah
|
|
|
Manie ###-#### remove rivits clip or install spreader bars plumb up wires
|
GCB-Framing | 8/19/2014 | 8/20/2014 | 8/20/2014 | A | DONE |
Dave Hannah
|
|
|
Manny ###-####
|
GCB-Framing | 8/19/2014 | 8/19/2014 | 8/19/2014 | P | PASS |
Jim Sly
|
|
|
Manny ###-####
|
GCB-Framing | 8/12/2014 | 8/13/2014 | 8/13/2014 | A | PART |
Dave Hannah
|
|
|
Requested partial framing for office. Will meet onsite to explain. Manny ###-#### office and high wall ok to cover.
|
Issue and Courier | | | 7/31/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 7/15/2014 | 7/15/2014 | 7/30/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
Routing - FIRE | 7/29/2014 | 7/15/2014 | 7/30/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-30-14
|
1st review completed | | | 7/30/2014 | | DONE |
|
|
|
Failed: Plan Check
|
Routing - PLAN CHECK | 7/30/2014 | | 7/30/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 7/29/2014 | | 7/29/2014 | | PASS |
Troy James
|
|
|
|
Routing - Plumbing Review | 7/29/2014 | | 7/29/2014 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - PLAN CHECK | 7/16/2014 | | 7/28/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Public Works | 7/15/2014 | 7/15/2014 | 7/16/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 6/24/2014 | | DONE |
|
|
|
|