GCB-Final | 3/11/2015 | 3/12/2015 | 3/12/2015 | P | PASS |
Dave Hannah
|
|
|
Ted ###-#### - if Ted not available, see Gordon
|
Issue and Courier | | | 2/17/2015 | | DONE |
Candy A. Nichols
|
|
|
called courier to pick up and take to GC
|
Plan assigned to (SRZ) | 7/3/2014 | 7/3/2014 | 2/13/2015 | | DONE |
Sam Zahorka
|
|
|
4th Review Completed. Pending Mechanical to pass.
|
Routing - Mechanical Review | 2/9/2015 | | 2/13/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 2/13/2015 | | 2/13/2015 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2015 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 1/6/2015 | | 2/9/2015 | | PASS |
Sam Zahorka
|
|
|
routed to Mechanical
|
Plan resubmittals received | | | 2/6/2015 | | DONE |
Candy A. Nichols
|
|
|
received resubmittals-3 sheets of A-1.1-took tof Sam Z
|
Routing - FIRE | 1/5/2015 | 1/5/2015 | 1/6/2015 | | PASS |
Scott Arellano
|
|
|
Approved with comments.
|
Routing - PLAN CHECK | 12/23/2014 | | 1/5/2015 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 12/23/2014 | | DONE |
Candy A. Nichols
|
|
|
resubmittals received-3 sheets of A-1.0-took to Sam Z
|
Routing - FIRE | 9/8/2014 | 9/8/2014 | 9/8/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 2 09/08/14
|
Routing - PLAN CHECK | 8/6/2014 | | 9/8/2014 | | PEND |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 9/8/2014 | | DONE |
Scott Arellano
|
|
|
Received Flammable and Combustible materials list from applicant via fax.
|
Routing - FIRE | 8/4/2014 | | 8/6/2014 | | FAIL |
Craig D. Hanson
|
|
|
Faxed and emailed resubmittal items to applicant. Attached Fire Code plan review report to case.
|
Routing - Mechanical Review | 7/31/2014 | | 8/4/2014 | | FAIL |
Troy James
|
|
|
previous review comments have not been addressed.
|
Routing - PLAN CHECK | 7/31/2014 | | 7/31/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 7/30/2014 | | |
|
|
|
1 copy of the following-fire code review, Material sheet on MID Temp Hardener, Material sheet on Multi Purpose Solvent, Material sheet on Corrosion Resistant Primer Catalyst, Material sheet on Corrosion Resistant Primer Grey, Material sheet on Axalta Coating Systems, and 1 set of plans the taken to Sam Zahorka's desk
|
1st review completed | | | 7/17/2014 | | DONE |
Sam Zahorka
|
|
|
Failed Building, Fire, and Mechanical
|
Routing - FIRE | 7/16/2014 | | 7/17/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 07-17-14
|
Routing - PLAN CHECK | 7/7/2014 | | 7/15/2014 | | FAIL |
Sam Zahorka
|
|
|
Incomplete plan submittals received.
|
Routing - Mechanical Review | 7/3/2014 | | 7/7/2014 | | FAIL |
Troy James
|
|
|
emailed comments to applicant
|
Application received | | | 6/30/2014 | | DONE |
|
|
|
|
Routing - Public Works | 7/3/2014 | 7/3/2014 | | | |
Beverly Mountain
|
|
|
|