GCB-Final | 10/1/2014 | 10/2/2014 | 10/2/2014 | P | PASS |
Dave Hannah
|
|
|
Zach ###-####0
|
FIRE-Final Inspection | 9/30/2014 | 10/1/2014 | 10/2/2014 | P | PASS |
Craig D. Hanson
|
|
|
Minor corrections no reinspection needed;
|
GCB-Final | 9/29/2014 | 9/30/2014 | 9/30/2014 | P | PART |
Dave Hannah
|
|
|
Arrielle ###-#### fire life saftey inspection and take care of ada issues
|
Routing - Plumbing Review | 9/3/2014 | | 9/5/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Plan assigned to (SRZ) | 7/15/2014 | 7/15/2014 | 9/4/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 9/4/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 9/3/2014 | | |
Sam Zahorka
|
|
|
received 3 sheets of P100-took to Sam Z
|
Routing - Plumbing Review | 8/21/2014 | | 8/27/2014 | | FAIL |
Bill VanDegrift
|
|
|
Provide complete set of engineered stamped plumbing plans showing locations and sizing.
|
Routing - PLAN CHECK | 8/12/2014 | | 8/21/2014 | | PASS |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 8/21/2014 | | DONE |
Candy A. Nichols
|
|
|
applicant brought in three sets of plan sheets marked: G001, G002, A200, EQ200, P200 as well as 1 transmittal and response letter;plans stamped and taken to SRZ
|
1st review completed | | | 8/12/2014 | | DONE |
|
|
|
Failed: Plan Check, plumbing
|
Routing - FIRE | 8/7/2014 | | 8/12/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-12-14
|
Routing - PLAN CHECK | 7/16/2014 | | 8/7/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 8/1/2014 | | 8/4/2014 | | PASS |
Troy James
|
|
|
|
Routing - Plumbing Review | 8/4/2014 | | 8/4/2014 | | FAIL |
Daryl Spivey
|
|
|
provide complete plumbing plans showing locations and sizes
|
Application received | | | 7/11/2014 | | DONE |
|
|
|
|