GCB-Final | 12/3/2014 | 12/4/2014 | 12/4/2014 | P | PASS |
Dave Hannah
|
|
|
Tom ###-####
|
GCB-Final | 11/14/2014 | 11/17/2014 | 11/17/2014 | P | NR |
Dave Hannah
|
|
|
Tom ###-####
|
GCB-Courtesy | 11/10/2014 | 11/10/2014 | 11/12/2014 | P | PASS |
Dave Hannah
|
|
|
Dennis ###-#### - requested a call before inspection
|
FIRE-Final Inspection | 10/28/2014 | 10/29/2014 | 10/29/2014 | A | PASS |
Craig D. Hanson
|
|
|
|
GCB-Framing | 10/22/2014 | 10/23/2014 | 10/23/2014 | A | PART |
Jim Sly
|
|
|
Tom ###-#### racking inspection requested; please see plan mod Racking OK.
|
Issue and Courier | | | 10/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (SRZ) | 10/20/2014 | 10/20/2014 | 10/20/2014 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 10/15/2014 | | 10/20/2014 | | PASS |
Sam Zahorka
|
|
|
|
Routing - FIRE | 10/14/2014 | 10/14/2014 | 10/15/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod 10-15-14
|
Plan resubmittals received | | | 10/14/2014 | | DONE |
Christina Prado
|
|
|
**PLAN MOD** Plan modification accepted for Racking installation. Received three sets of revised application, structural calcs & plans
|
FIRE-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Craig D. Hanson
|
|
|
|
GCB-Final | 9/29/2014 | 9/30/2014 | 9/30/2014 | P | PEND |
Dave Hannah
|
|
|
Tom ###-#### please call to meet onsite needs to fix ada sidewalk at front door/landing
|
FIRE-Final Inspection | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | CANC |
Craig D. Hanson
|
|
|
Steve Phone #: ###-####///cancelled per request from Erika @Garden City
|
GCB-Framing | 9/9/2014 | 9/10/2014 | 9/10/2014 | P | PASS |
Jim Sly
|
|
|
Tom ###-####
|
GCB-Framing | 9/5/2014 | 9/8/2014 | 9/9/2014 | P | PART |
Dave Hannah
|
|
|
Tom ###-#### ok to cover in fill openings in shop wall
|
Issue and Courier | | | 8/13/2014 | | DONE |
Barbara Stitt
|
|
|
|
Routing - FIRE | 8/12/2014 | 8/12/2014 | 8/12/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-12-14
|
Plan assigned to (SRZ) | 7/16/2014 | 7/16/2014 | 8/12/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed
|
Plan resubmittals received | | | 8/12/2014 | | DONE |
Sam Zahorka
|
|
|
Received sheets A0.0, A2.1, & A2.2.
|
Routing - PLAN CHECK | 8/12/2014 | | 8/12/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2014 | | DONE |
Sam Zahorka
|
|
|
|
1st review completed | | | 8/4/2014 | | DONE |
Sam Zahorka
|
|
|
Failed Building and Fire
|
Routing - FIRE | 8/1/2014 | | 8/4/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-04-14
|
Routing - PLAN CHECK | 7/17/2014 | | 8/1/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Public Works | 7/16/2014 | 7/16/2014 | 7/17/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 7/15/2014 | | DONE |
|
|
|
|