GCB-Final | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PASS |
Jim Sly
|
|
|
Vaughn ###-#### Final Structural......OK.
|
GCB-Final | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | FAIL |
Mike Jordan
|
|
|
Vaughn ###-####. Provide handrail extensions and handrail to be continous at mezz. Provide ADA portion at bar, mens room toilet flusher to be on turning radius side, post live load sign at mezz.
|
FIRE-Final Inspection | 9/22/2015 | 9/22/2015 | 9/22/2015 | P | PASS |
Katie Marron
|
|
|
Previous notice items have been corrected. Lift safety pass.
|
FIRE-Final Inspection | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide plan review approval for deleting the west exit door/exit sign/emergency light, provide exit sign/emergency light at the top of the stairs as per plans, repair the two Tasting Area exit signs and exit discharge lights, provide ADA hardware for the small cooler under the mezzanine.
|
GCB-Framing | 8/3/2015 | 8/4/2015 | 8/4/2015 | A | CANC |
Mike Jordan
|
|
|
Vaughn ###-#### - call for access
|
Plan assigned to (CDM) | 5/14/2015 | 5/14/2015 | 8/3/2015 | | DONE |
Carl D Madsen
|
|
|
First review completed
|
GCB-Framing | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | PASS |
Mike Jordan
|
|
|
Vaughn ###-####. Stairs and guard rails ok, needs to install code compliant handrails.
|
GCB-Framing | 7/2/2015 | 7/6/2015 | 7/6/2015 | A | PART |
Dave Hannah
|
|
|
Vaughn ###-#### - requested call ahead ok to cover the cold storage area and rest rooms stairs are out of code rise is over 7 inchs and gaurd rail is under 42 inchs
|
Routing - PLAN CHECK | 7/1/2015 | | 7/1/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/2015 | | DONE |
|
|
|
|
Issue and Courier | | | 7/1/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/25/2015 | | 6/26/2015 | | FAIL |
Carl D Madsen
|
|
|
Additional engineering is required for the new RTU's that wer not part of the original roof design heating and cooling previously utililized mini-split units with remote fan coils.
|
Plan resubmittals received | | | 6/26/2015 | | DONE |
|
|
|
resubmittals-rescieved 3 sheets of A1.1-took to Carl M
|
Plan resubmittals received | | | 6/26/2015 | | DONE |
|
|
|
resubmittals recieved 3 of each sheet E2.0L, E2.OMP, E2.0P, E3.2-Took to Carl M
|
Routing - Mechanical Review | 6/24/2015 | | 6/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - Plumbing Review | 6/22/2015 | | 6/24/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Plan resubmittals received | | | 6/22/2015 | | DONE |
|
|
|
resubmittals recieved 3 sets of sheets M1.0, M2.0, M3.0, P3.0-Took to Carl M
|
Routing - PLAN CHECK | 5/21/2015 | | 6/21/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Plumbing Review | 5/26/2015 | | 5/27/2015 | | FAIL |
Daryl Spivey
|
|
|
Required to seperate water for public use from brewery equipment water as provided in first submitted plan.
|
Routing - Mechanical Review | 5/21/2015 | | 5/26/2015 | | PASS |
Troy James
|
|
|
|
Routing - Public Works | 5/21/2015 | 5/21/2015 | 5/21/2015 | | PASS |
Beverly Mountain
|
|
|
|
Plan resubmittals received | | | 5/14/2015 | | DONE |
|
|
|
plan mod received 3 of each sheetA1.1, E.0L, E.OMP, E.OP, E3, M2.0, P1.0, P2.0 & P3.0-took to Carl m
|
GCB-Framing | 4/16/2015 | 4/16/2015 | 4/16/2015 | P | PASS |
Jim Sly
|
|
|
Vaughn ###-####
|
GCB-Masonry | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | PART |
Jim Sly
|
|
|
John ###-#### - requested call ahead Looked at N. S. and W. 3' high walls. Looked at 1st 6' of tall walls at overhead door. Appears OK. Called Engineer of record.......He wants special inspection on all CMU. Special inspection to be done before grout pour........Notified Contractor.
|
GCB-Fndatn/slab ins/fld vent | 3/5/2015 | 3/5/2015 | 3/5/2015 | P | PASS |
Dave Hannah
|
|
|
Wesley ###-#### - requests 1p.m. inspection
|
GCB-Fndatn/slab ins/fld vent | 2/20/2015 | 2/23/2015 | 2/23/2015 | A | PEND |
Jim Sly
|
|
|
Wesley ###-#### - requested late AM insp.
|
GCB-Footing | 2/23/2015 | 2/23/2015 | 2/23/2015 | P | PASS |
Jim Sly
|
|
|
Wesley ###-#### OK pending MTI special insp, tests and approvals.
|
GCB-Footing | 2/20/2015 | 2/23/2015 | 2/23/2015 | A | PEND |
Jim Sly
|
|
|
Wesley ###-#### - requested late a.m. insp. Re-sched........
|
GCB-Footing | 2/19/2015 | 2/20/2015 | 2/20/2015 | P | NR |
Jim Sly
|
|
|
Ryan ###-#### - requested late p.m. inspection Not ready...... Still installing forms.......No special inspection completed.
|
GCB-Courtesy | 2/13/2015 | 2/13/2015 | 2/14/2015 | P | PASS |
Dave Hannah
|
|
|
Vaughn Pruett ###-#### - requested call ahead
|
Issue and Courier | | | 11/19/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (SRZ) | | 9/18/2014 | 11/18/2014 | | DONE |
Sam Zahorka
|
|
|
Pending Structural to pass.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/5/2014 | | 11/18/2014 | | PASS |
Sam Zahorka
|
|
|
|
Routing Off Site - STRUCTURAL | 11/18/2014 | | 11/18/2014 | | PASS |
Sam Zahorka
|
|
|
emailed corrected calculations
|
Routing - Mechanical Review | 11/18/2014 | | 11/18/2014 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 11/17/2014 | | DONE |
Candy A. Nichols
|
|
|
received 3 sets of m1.0, m2.0, m3.0, p1.0, p2.0, p3.0, 2 struc review sheets, 3 sets of clacs, 1 1 mechanical engineering from Tikker Enginering & took to Sam Z
|
Routing Off Site - STRUCTURAL | 11/4/2014 | | 11/7/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 11/5/2014 | 11/5/2014 | 11/5/2014 | | PASS |
Scott Arellano
|
|
|
Attached Fire Code comments to plans.
|
Routing - Mechanical Review | 11/4/2014 | | 11/5/2014 | | FAIL |
Troy James
|
|
|
emailed corrections to applicant and mechanical engineer
|
Telephone call | | | 11/4/2014 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Plan resubmittals received | | | 10/31/2014 | | DONE |
Christina Prado
|
|
|
Received three sets of revised plan sheets marked M2.0, S0, S1, S2, S3 & S4 as well as three sets revised NACFR review comments, three sets revised mechanical review comments and three sets revised tructural review comments; Plans taken to SRZ for review and assignment
|
Routing - PLAN CHECK | 10/7/2014 | | 10/22/2014 | | PEND |
Sam Zahorka
|
|
|
Pending Fire, Mechanical, and Structural to pass.
|
Telephone call | | | 10/22/2014 | | DONE |
Sam Zahorka
|
|
|
Called the architect and left a message. Never received structural corrections to route to Structural plan review.
|
Plan resubmittals received | | | 10/20/2014 | | DONE |
Candy A. Nichols
|
|
|
received 3 sets of sheet # A1.1, A2.2, & 1 set of plan reviewer comments took to Sam Z
|
Telephone call | | | 10/16/2014 | | DONE |
Candy A. Nichols
|
|
|
called Action Couriers to pick up revised plans @ GC and bring to us
|
Plan resubmittals received | | | 10/16/2014 | | DONE |
Candy A. Nichols
|
|
|
received 1 set of GC plan review, 1 set of ALCollaborative & 3 sets of sheet G1.0, SD1.1, A1.1, A2.2, L1.0, L1.1 & L2.0-took to Sam
|
Routing - Plumbing Review | 10/6/2014 | | 10/7/2014 | | PASS |
Bill VanDegrift
|
|
|
May require additional backflow protection on installed equipment.
Per plan and ISPC.
|
Routing - PLAN CHECK | 10/3/2014 | | 10/6/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 10/3/2014 | | DONE |
Candy A. Nichols
|
|
|
recieved resubmitted plans 4 sheets of P1.0 & P2.0-took to Sam Z.
|
Routing - FIRE | 9/25/2014 | | 10/1/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-01-14
|
1st review completed | | | 10/1/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/25/2014 | | 9/30/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing Off Site - STRUCTURAL | 9/26/2014 | | 9/30/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 9/26/2014 | | DONE |
Christina Prado
|
|
|
Received four sets of revised structural calcs for two seperate buildings;Docs stamped and taken to Sam for further review
|
Routing - Mechanical Review | 9/19/2014 | | 9/25/2014 | | FAIL |
Troy James
|
|
|
emailed corrections to applicant
|
Routing - Public Works | 9/18/2014 | 9/18/2014 | 9/19/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 9/15/2014 | | DONE |
|
|
|
via Garden City Web Service
|