GCB-Final | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | PASS |
Dave Hannah
|
|
|
Robert ###-####
|
GCB-Final | 2/23/2015 | 2/23/2015 | 2/24/2015 | P | PART |
Dave Hannah
|
|
|
Zack ###-#### needs fire final and fix ada issues
|
FIRE-Final Inspection | 2/23/2015 | 2/23/2015 | 2/23/2015 | P | PASS |
Scott Arellano
|
|
|
Call prior to going Phone #: ###-#### >> Inspection requested via mobile web by Zack Caper
3 hour fire door not installed. Infilled opening within 4 hour fire wall to be approved by structural inspector.
|
GCB-Framing | 12/17/2014 | 12/17/2014 | 12/18/2014 | P | PASS |
Dave Hannah
|
|
|
Zack ###-#### - cover insp.
|
GCB-Framing | 12/16/2014 | 12/16/2014 | 12/16/2014 | P | FAIL |
Dave Hannah
|
|
|
Brian ###-#### - access at corner of 34th and Brown needs to fire block wall and fur downs
|
Plan assigned to (SRZ) | 11/4/2014 | 11/4/2014 | 11/10/2014 | | DONE |
Sam Zahorka
|
|
|
Pending Statement for Special Inspections
|
CHANGE STATUS TO (ISS) | | | 11/10/2014 | | DONE |
Sam Zahorka
|
|
|
|
CHANGE STATUS TO (REV) | | | 11/4/2014 | | DONE |
Sam Zahorka
|
|
|
Waiting for a Statement for Special Inspection
|
Plan assigned to (SRZ) | | 9/22/2014 | 10/31/2014 | | DONE |
Sam Zahorka
|
|
|
2nd review completed.
|
Routing - PLAN CHECK | 10/15/2014 | | 10/31/2014 | | FAIL |
Sam Zahorka
|
|
|
Pending accessible upgrade letter from the architect.
|
Routing - PLAN CHECK | 10/31/2014 | | 10/31/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2014 | | DONE |
Sam Zahorka
|
|
|
|
Issue and Courier | | | 10/31/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 10/28/2014 | | DONE |
Candy A. Nichols
|
|
|
received from GC by courier 1 response letter from TAO Architects and 2 sets of sheet # A.00, A2.0, A2.1, A2.2, A2.3, A4.0, A6.0, A7.0, M1.0, M2.0,& M3.0- took tof Sam Z
|
1st review completed | | | 10/15/2014 | | DONE |
|
|
|
Failed: Plan Check
|
Routing - FIRE | 10/10/2014 | | 10/15/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-15-14
|
Routing - PLAN CHECK | 10/1/2014 | | 10/10/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Mechanical Review | 9/24/2014 | | 10/1/2014 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 9/30/2014 | | DONE |
Christina Prado
|
|
|
Received three sets of revised plan sheets marked M1.0, M2.0 & M3.0;Plans stamped and taken to Sam Zahorka for review
|
Routing - Public Works | 9/22/2014 | 9/22/2014 | 9/24/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 9/22/2014 | | DONE |
|
|
|
via Garden City Web Service
|