GCB-Final | 11/4/2015 | 11/4/2015 | 11/4/2015 | P | PASS |
Tony Young
|
|
|
Manny ###-#### code: 9981
|
GCB-Shearwall | 5/28/2015 | 5/28/2015 | 5/28/2015 | P | PASS |
Phil Shearer
|
|
|
Mark ###-####
|
GCB-Energy | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Phil Shearer
|
|
|
Mark ###-#### - requested call ahead and late PM insp.
|
GCB-Framing | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Phil Shearer
|
|
|
Mark ###-#### - requested call ahead and late PM insp.
|
GCB-Framing | 5/11/2015 | 5/12/2015 | 5/12/2015 | A | PART |
Phil Shearer
|
|
|
Mark ###-#### - requested call ahead. Fire caulking on penetrations through fire wall OK.
|
GCB-Framing | 5/8/2015 | 5/8/2015 | 5/8/2015 | P | PART |
Phil Shearer
|
|
|
Mark ###-#### - requested call ahead. Truss bracing OK all other corrections in progress OK to insulate
|
GCB-Framing | 5/7/2015 | 5/7/2015 | 5/7/2015 | P | NR |
Tony Young
|
|
|
Mark ###-#### - requested call ahead
|
GCB-Framing | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | FAIL |
Mike Jordan
|
|
|
Mark ###-####. No wall bracing inspection, a wall bracing inspection is required. Can not verifiy construction of 2hr. firewalls, no inspections called in during their construction, to verifiy attachment and continuity. A current elevation cert is required. Could not locate truss engineering. Fireblock all concealed spaces upstairs and downstairs. laydown parapet shall extend to firewall.
|
GCB-Fndatn/slab ins/fld vent | 12/9/2014 | 12/10/2014 | 12/10/2014 | P | PASS |
Jim Sly
|
|
|
Mana ###-####
|
GCB-Fndatn/slab ins/fld vent | 12/8/2014 | 12/9/2014 | 12/9/2014 | P | NR |
Jim Sly
|
|
|
Mana ###-####
|
GCB-Footing | 12/5/2014 | 12/8/2014 | 12/9/2014 | P | PASS |
Dave Hannah
|
|
|
Mana ###-#### - requested 1p.m.
|
Plan assigned to (SRZ) | | 10/31/2014 | 11/14/2014 | | DONE |
Sam Zahorka
|
|
|
1st review completed
|
Routing - PLAN CHECK | 11/14/2014 | | 11/14/2014 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2014 | | DONE |
Sam Zahorka
|
|
|
|
Plan resubmittals received | | | 11/13/2014 | | DONE |
Candy A. Nichols
|
|
|
received resubmitted plans from GC by courier- 3 sets of sheet 0.0, 1.0, 2.0, 3.0, 3.1, 4.0, 4.1, 5.0, S1.0, S1.1, E1.0-took to Sam Z
|
1st review completed | | | 11/7/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/3/2014 | | 11/7/2014 | | FAIL |
Sam Zahorka
|
|
|
Pending adjacent townhouse to pass or provide separate plans for this one.
|
Routing - Mechanical Review | 10/31/2014 | | 11/3/2014 | | PASS |
Troy James
|
|
|
|
Application received | | | 10/29/2014 | | DONE |
|
|
|
via Garden City Web Service
|