GCB-Final | 1/20/2015 | 1/21/2015 | 1/22/2015 | P | PASS |
Dave Hannah
|
|
|
Tom ###-####
|
FIRE-Final Inspection | 1/20/2015 | 1/21/2015 | 1/21/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
GCB-Framing | 1/7/2015 | 1/7/2015 | 1/7/2015 | P | PART |
Dave Hannah
|
|
|
Tom ###-#### sheet rock on fire walls both sides ok to cover
|
GCB-Framing | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | PART |
Dave Hannah
|
|
|
Tom ###-#### ok to sheetrock inside of back wall
|
Plan assigned to (TLW) | 11/21/2014 | | 12/5/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 12/5/2014 | | 12/5/2014 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2014 | | DONE |
|
|
|
|
Issue and Courier | | | 12/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan resubmittals received | | | 12/2/2014 | | DONE |
Candy A. Nichols
|
|
|
received by colurier from GC-1 CD , 1 transmittla sheet,1 set of engineering calcs,3 sheets of A2.0-took to Tim W
|
Plan assigned to (SRZ) | | 11/12/2014 | 11/21/2014 | | DEFR |
Sam Zahorka
|
|
|
|
Routing - FIRE | | 11/12/2014 | 11/21/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 11-21-14
|
Routing - Public Works | 11/12/2014 | 11/12/2014 | 11/21/2014 | | PASS |
Beverly Mountain
|
|
|
Approved under GCB14-00162. TLW
|
Routing - PLAN CHECK | 11/18/2014 | | 11/21/2014 | | FAIL |
Sam Zahorka
|
|
|
Plans Reassigned to TLW on 11-19-2014. Resubmittals required. TLW
|
1st review completed | | | 11/21/2014 | | DONE |
|
|
|
|
Routing - Mechanical Review | | | 11/18/2014 | | PASS |
Troy James
|
|
|
no mechanical to review
|
Application received | | | 11/10/2014 | | DONE |
|
|
|
via Garden City Web Service
|